VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 SHUTTLE COUNTDOWN (LPS) MAT COPY | DRAFT COPY ---------- RECIPIENT(S) SHALL REVIEW THIS COPY AND SUBMIT INPUT TO: SFOC OMD:____________________ RM:________ EXT:________ DATE:_______ PRELIMINARY REVIEW COPY ----------------------- RECIPIENTS SHALL REVIEW THIS COPY, COORDINATE INPUT WITH CUSTOMER COUNTERPARTS AND BRING MARKED UP COPY OF JOINT FUNCTIONAL INPUT TO THE REVIEW MEETING SCHEDULED FOR: DATE:__________ TIME:__________ RM:__________ FINAL REVIEW SIGNOFF COPY ------------------------- RECIPIENTS SHALL REVIEW THIS COPY, COORDINATE INPUT WITH CUSTOMER COUNTERPARTS AND BRING MARKED UP COPY OF JOINT FUNCTIONAL INPUT TO SIGNOFF REVIEW MEETING SCHEDULED FOR: DATE:__________ TIME:__________ RM:__________ PAGE BREAK COPY --------------- RECIPIENT(S) SHALL REVIEW THIS COPY AND SUBMIT INPUT TO: SFOC OMD:____________________ RM:________ EXT:________ DATE:_______ NOTE IN EVENT OF A DISCREPANCY, THE PUBLISHED OMI REVIEW MEETING SCHEDULE TAKES PRECEDENCE OVER THIS SCHEDULE. OMI TECHNICAL CONTACT: ROGER GILLETTE, 1-7437 | OMI WRITER: PAM STIELER, 1-4958 DISTRIBUTION PER ATTACHED DISTRIBUTION LIST ------------------------------------------------------------------ THIS PROCEDURE CONTAINS HAZARDOUS OPERATIONS ------------------------------------------------------------------ VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 UNITED SPACE ALLIANCE ******************************************************** * * * SHUTTLE COUNTDOWN (LPS) * * * ******************************************************** * EFFECTIVITY CATEGORY: A * * HA-VTBAMQDG * * SCWZF+ER * * CENTER: KSC * * SYSTEM: TCO * * SITE: PAD A/B * * * * VEHICLE: OV-102,103,104,105 * * * * FLOW: ALL * * * * DESIGN CENTER CONCURRENCE: JSC & MSFC * ******************************************************** | PREPARED BY: _________________________________ SFOC TEST DOCUMENTATION APPROVED BY: CONTRACTOR _________________________________ SFOC SAFETY ENGINEERING ------------------------------------------------------------------ THIS PROCEDURE CONTAINS HAZARDOUS OPERATIONS ------------------------------------------------------------------ VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 ******************************************************** * * * SHUTTLE COUNTDOWN (LPS) * * * ******************************************************** * EFFECTIVITY CATEGORY: A * * HA-VTBAMQDG * * SCWZF+ER * * CENTER: KSC * * SYSTEM: TCO * * SITE: PAD A/B * * * * VEHICLE: OV-102,103,104,105 * * * * FLOW: ALL * * * * DESIGN CENTER CONCURRENCE: JSC & MSFC * ******************************************************** VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 UNITED SPACE ALLIANCE ******************************************************** * * * SHUTTLE COUNTDOWN (LPS) * * * ******************************************************** * EFFECTIVITY CATEGORY: A * * HA-VTBAMQDG * * SCWZF+ER * * CENTER: KSC * * SYSTEM: TCO * * SITE: PAD A/B * * * * VEHICLE: OV-102,103,104,105 * * * * FLOW: ALL * * * * DESIGN CENTER CONCURRENCE: JSC & MSFC * ******************************************************** PREPARED BY: _________________________________ SFOC TEST DOCUMENTATION APPROVED BY: CONTRACTOR GOVERNMENT _________________________________ ___________________________ SFOC OPR SM _________________________________ SFOC SAFETY ENGINEERING ------------------------------------------------------------------ THIS PROCEDURE CONTAINS HAZARDOUS OPERATIONS ------------------------------------------------------------------ VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 REVISION RECORD PAGE -------------------- REV-CHANGE DATE REASON PAGES AFFECTED EFFECTIVITY ------------------------------------------------------------------- AS : 10-02-98 : 127/USK217: ALL : STS-95&SUBS : : RCN : : : : OV13313 : : -------------------------------------------------------------------- AS-1 : 11-13-98 : 128/USK023: 8-13,39,60,73-78, : STS-88&SUBS : : RCN : 90,91,96,97,102, : : : KG02038 : 103,106,143,146, : : : : 154,156,176,179, : : : : 180,217,218,338, : : : : 339,341,342,345, : : : : 346,348,349,352, : : : : 393,505,508,508.1, : : : : 508.2,509,509.1, : : : : 509.2,510,550, : : : : 550.1,550.2,551, : : : : 583,621,626,632 : -------------------------------------------------------------------- AT : 04-28-99 : 129/USK206: ALL : STS-96&SUBS -------------------------------------------------------------------- | AT-1 : 07-01-99 : 130/USK217: 9-15,17,59,60,73, : STS-93&SUBS | : : : 74,78-82,82.1,82.2 : | : : : 93,101,106 : | : : : 106.1,106.2,263,273: | : : : 273.1,273.2,283-290: | : : : 311,311.1,311.2,320: | : : : 351,421,447,448,617: | : : : 633 : | -------------------------------------------------------------------- VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 BACKUP SIGNATURE SHEET OMI TITLE: SHUTTLE COUNTDOWN (LPS) AGENCY SIGNATURES SYSTEM CONTRACTOR/NASA CONTRACTOR GOVERNMENT ------ --------------- ---------- ---------- SUPPORT ------- TSMO SFOC ___________________ NA TIMING/ COUNTDOWN CSR ___________________ NA RPS SFOC/NASA ___________________ ________________ LPS SFOC/NASA ___________________ ________________ ETR PAA/SRO ___________________ NA MEASUREMENTS SFOC/NASA ___________________ ________________ PHOTO BIONETICS ___________________ NA MILA BFEC/GUSB ___________________ NA VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 BACKUP SIGNATURE SHEET OMI TITLE: SHUTTLE COUNTDOWN (LPS) AGENCY SIGNATURES SYSTEM CONTRACTOR/NASA CONTRACTOR GOVERNMENT ------ --------------- ---------- ------------ PAYLOAD ------- TEST PGOC ___________________ NA CONDUCTOR PAYLOAD PGOC /CS-PPD-1 ___________________ ________________ INTEG ENGR ELECT INTEG PGOC ___________________ ________________ SOFTWARE PGOC ___________________ ________________ IUS BAO/6555TH ___________________ ________________ MIDDECK CS-EED-1 NA ________________ EXP ULS ESA ___________________ NA VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 BACKUP SIGNATURE SHEET OMI TITLE: SHUTTLE COUNTDOWN (LPS) AGENCY SIGNATURES SYSTEM CONTRACTOR/NASA CONTRACTOR GOVERNMENT ------ --------------- ---------- ---------- ORBITER ------- NAVAIDS SFOC/NASA ___________________ ________________ COMM SFOC/NASA ___________________ ________________ INSTR SFOC/NASA ___________________ ________________ HGDS SFOC/NASA ___________________ ________________ PVD SFOC/NASA ___________________ ________________ LAUNCH ACC SFOC/NASA ___________________ ________________ EPD&C SFOC/NASA ___________________ ________________ DPS SFOC/NASA ___________________ ________________ DPSME SFOC/NASA ___________________ ________________ QE SFOC ___________________ NA CARGO/EXP SFOC/NASA ___________________ ________________ MPS SFOC/NASA ___________________ ________________ APU SFOC/NASA ___________________ ________________ HYDRAULICS SFOC/NASA ___________________ ________________ SAFETY SFOC ___________________ NA VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 BACKUP SIGNATURE SHEET OMI TITLE: SHUTTLE COUNTDOWN (LPS) AGENCY SIGNATURES SYSTEM CONTRACTOR/NASA CONTRACTOR GOVERNMENT ------ --------------- ---------- ---------- ORBITER (CONT) -------------- PRSD SFOC/NASA ___________________ ________________ MECH/STRUC SFOC/NASA ___________________ ________________ OMS/RCS SFOC/NASA ___________________ ________________ ECLSS SFOC/NASA ___________________ ________________ TPE/PEO SFOC/NASA ___________________ ________________ VITT NASA/JSC NA ________________ TPS SFOC/NASA ___________________ ________________ FCS SFOC/NASA ___________________ ________________ G&N SFOC/NASA ___________________ ________________ FLT CNTLS SFOC/NASA ___________________ ________________ ORB SOFTWARE SFOC/NASA ___________________ ________________ PYRO SFOC/NASA ___________________ ________________ GLS SFOC/NASA ___________________ ________________ LO DATA SFOC/NASA ___________________ ________________ SSME QE ROCKETDYNE ___________________ NA TPS QE SFOC ___________________ NA VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 BACKUP SIGNATURE SHEET OMI TITLE: SHUTTLE COUNTDOWN (LPS) AGENCY SIGNATURES SYSTEM CONTRACTOR/NASA CONTRACTOR GOVERNMENT ------ --------------- ---------- ---------- EXTERNAL TANK ET/SRB -------------------- TEST COND SFOC/(ROR) ___________________ NA PROJ ENGR SFOC ___________________ NA ELECTRICAL SFOC/NASA ___________________ ________________ (SRB) INSTR SFOC/NASA ___________________ ________________ MECH(ET) SFOC/NASA ___________________ ________________ PROPELLANTS/ LO2 SFOC/NASA ___________________ ________________ PROPELLANTS/ LH2 SFOC/NASA ___________________ ________________ DPS SFOC/NASA ___________________ ________________ HYD SFOC/NASA ___________________ ________________ EPDC SFOC/NASA ___________________ ________________ MECH (SRB) SFOC/NASA ___________________ ________________ SRSS SFOC/NASA ___________________ ________________ VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 DESIGN CENTER CONCURRENCE BACKUP SIGNATURE SHEET ------------------------- OMI TITLE: SHUTTLE COUNTDOWN (LPS) AGENCY SIGNATURES SYSTEM CONTRACTOR/NASA CONTRACTOR* NASA ------ --------------- ----------- ------------ ORBITER ORBITER ENGR ___________________ NA SSP SYS INTEG SYSTEM INTEG ___________________ NA SSP KSC SPACE SHUTTLE KSC INTEG INTEG (ML-SIO) NA ________________ SSP CARGO INTEG CARGO INTEG ___________________ NA SSP CARGO SPACE SHUTTLE SYS INTEG INTEG (MS) NA ________________ * LSS REVIEWS ARE PER THE LIMITATIONS CONTAINED WITHIN THEIR RESPECTIVE MEMORANDA OF UNDERSTANDING WITH THE SPC. VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 TABLE OF CONTENTS ----------------- PAGE ---- COVER PAGE APPROVAL PAGE/CHANGE RECORD PAGE TABLE OF CONTENTS OBJECTIVE/DESCRIPTION ..................................... 1 ILLUSTRATIONS ............................................. 3 HAZARDOUS MANLOADING ...................................... NA BAR CHARTS ................................................ NA SECTION I - INFORMATION 1.1 REFERENCED INSTRUCTIONS........................... 7 1.2 COMPUTER SYSTEMS.................................. 15 1.3 SPECIAL TOOLS, EQUIPMENT AND MATERIALS............ 19 1.4 SUPPORT TOOLS, EQUIPMENT AND MATERIALS............ 33 1.5 PERSONNEL REQUIREMENTS............................ 66 1.6 SAFETY REQUIREMENTS............................... 67 1.7 SPECIAL INSTRUCTIONS.............................. 69 1.8 OMRS REQUIREMENTS SATISFIED BY THIS TOP........... 78 SECTION II - PRE-OPERATION SETUP INSTRUCTIONS 01-000 PRE-OPERATION SETUPS - SUPPORT................ 83 01-001 PRE-OPERATION SETUP 1 - PRE-OPERATION SETUP SUMMARY SHEET................................ 83 01-004 PRE-OPERATION SETUP 2 - SUPPORT PREPARATIONS.. 85 01-113 PRE-OPERATION SETUP 3 - LAUNCH STATUS AND HOLD TIME REMAINING CLOCKS........................ 129 01-117 PRE-OPERATION SETUP 4 - LPS FEP BASELINE RELOAD........................................ 131 01-168 PRE-OPERATION SETUP 5 - PRSD LO2/LH2 TANKER PREPS........................................ 143 01-171 PRE-OPERATION SETUP 6 - LCC2 HSP1 LAUNCH SUPPORT CONFIGURATION........................ 145 01-180 PRE-OPERATION SETUP 7 - COMMUNICATION SUPPORT 147 01-189 PRE-OPERATION SETUP 8 - POLE CES ASSY LIFT TO 195 FT LEVEL OF FSS.......................... 149 01-207 PRE-OPERATION SETUP 9 - SRB FLAME DEFLECTOR MOVE TO LAUNCH POSITION (M3184).............. 155 01-221 PRE-OPERATION SETUP 10 - MLP/PAD SS I/F CONNECTIONS AND WATER TROUGH INSTALLATION/FILL 159 01-231 PRE-OPERATION SETUP 11- WASHDOWNS............ 162 01-244 PRE-OPERATION SETUP 12 - LPS RCVS S0007 TABLE LOAD.......................................... 165 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 02-000 PRE-OPERATION SETUPS - ORBITER................ 167 02-001 PRE-OPERATION SETUP 1 - PRE-OPERATION SETUP SUMMARY SHEET................................ 167 02-004 PRE-OPERATION SETUP 2 - ENGINEERING WALKDOWN.. 171 02-010 PRE-OPERATION SETUP 3 - WIDEBAND PATCHING - MADS FDM VERIF - OLSA........................ 173 02-014 PRE-OPERATION SETUP 4 - CABIN HATCH SEAL UNIT PREPS........................................ 175 02-019 PRE-OPERATION SETUP 5 - WASTE WATER DRAIN HOSE AND DISCONNECT ASSY.......................... 177 02-023 PRE-OPERATION SETUP 6 - C70-1226-3 CABIN PRESSURIZATION PANEL PREPS.................... 179 02-034 PRE-OPERATION SETUP 7 - S70-1203 ADJUST...... 183 02-044 PRE-OPERATION SETUP 8 - FLIGHT CREW SYSTEM STOWAGE PRIOR TO MVAK INSTALLATION (WITH MIDDECK PLATFORMS REMOVED).................... 191 02-049 PRE-OPERATION SETUP 9 - LAUNCH ACCESSORIES SYS TSM INITIAL PREPS (V3517/V3518).............. 193 02-054 PRE-OPERATION SETUP 10 - ECS LOCAL OPERATIONS (V1122)...................................... 195 02-058 PRE-OPERATION SETUP 11 - PRELIMINARY INSPECTION OF CREW MODULE INTERIOR (FLT DECK/MID DECK)................................ 197 02-077 PRE-OPERATION SETUP 12 - GSE PURGE VERIFICATION (V5052).......................... 201 02-080 PRE-OPERATION SETUP 13 - WINDOW COVER REMOVAL, CLEANING AND INSPECTION...................... 203 02-097 PRE-OPERATION SETUP 14 - OMS QUANTITY GAGING CHECKS........................................ 215 02-117 PRE-OPERATION SETUP 15 - ANTENNA COUPLER INSTALLATION.................................. 225 02-124 PRE-OPERATION SETUP 16 - PRSD LOADING PREPS.. 227 02-128 PRE-OPERATION SETUP 17 - FIBER OPTIC UPLINK MONITOR SYSTEM ACTIVATION.................... 229 02-135 PRE-OPERATION SETUP 18 - MISSION UNIQUE CREW COMPARTMENT CONFIGURATION.................... 231 02-139 PRE-OPERATION SETUP 19 - AFT FLIGHT DECK/ MIDDECK PLATFORM REMOVAL...................... 233 02-146 PRE-OPERATION SETUP 20 - WMS-FINAL STOWAGE (V5097.002).................................. 237 02-149 PRE-OPERATION SETUP 21 - FLIGHT CREW SYSTEM STOWAGE...................................... 239 02-156 PRE-OPERATION SETUP 22 - OME GN2 REG OUT ADJUSTMENT.................................... 241 02-165 PRE-OPERATION SETUP 23 - TACAN SIGNAL MONITOR SETUP - C&T STATION.......................... 247 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 03-000 PRE-OPERATION SETUPS - ET.................... 249 03-001 PRE-OPERATION SETUP 1 - PRE-OPERATION SETUP SUMMARY SHEET................................ 249 03-004 PRE-OPERATION SETUP 2 - GROUND POWER AND HEATER PREPARATIONS.......................... 251 03-010 PRE-OPERATION SETUP 3 - HYDROGEN SAMPLE LINE FIT CHECK.................................... 253 03-014 PRE-OPERATION SETUP 4 - HWS REMOTE LEAK DETECTOR CALIBRATION GAS CYLINDER AND VALVE CHECKS........................................ 255 03-033 PRE-OPERATION SETUP 5 - HWS REMOTE LEAK DETECTOR SYSTEM PRETEST VERIFICATIONS........ 263 03-089 PRE-OPERATION SETUP 6 - PAD FIRE DETECTOR ALIGNMENT.................................... 283 04-000 PRE-OPERATION SETUPS - SRB.................... 293 04-001 PRE-OPERATION SETUP 1 - PRE-OPERATION SETUP SUMMARY SHEET................................ 293 04-004 PRE-OPERATION SETUP 2 - JOINT HEATER DISCONNECT SWITCH CONFIGURATION.............. 295 04-009 PRE-OPERATION SETUP 3 - SRB QUALITY INSPECTION 297 04-015 PRE-OPERATION SETUP 4 - SRB ESP OPERATIONS.... 299 04-051 PRE-OPERATION SETUP 5 - ER CIRCUIT PATCHING.. 309 04-056 PRE-OPERATION SETUP 6 - SRB AFT SKIRT GN2 PURGE SKID ACTIVATION........................ 311 05-000 PRE-OPERATION SETUPS - INTEGRATED............ 319 05-001 PRE-OPERATION SETUP 1 - SAFETY/FACILITY/ FIRE WALKDOWN...................................... 319 05-013 PRE-OPERATION SETUP 2 - SAFETY PREPS.......... 325 06-000 PRE-OPERATION SETUPS - PAYLOAD................ 327 06-001 PRE-OPERATION SETUP 1 - RESERVED.............. 327 SECTION III - OPERATION SUPPORT SETUP INSTRUCTIONS 07-000 OPERATION SUPPORT SETUPS - SUPPORT............ 329 07-001 OPERATION SUPPORT SETUP 1 - TAIR TRAILER MOVE 329 07-012 OPERATION SUPPORT SETUP 2 - LCC2 LAUNCH SUPPORT CONFIGURATION - LPS T-11 HOUR BIH TO T+45 MIN...................................... 335 07-028 OPERATION SUPPORT SETUP 3 - FALLBACK CONFIGURATION - SUPPORT RED CREW T-6 HRS THRU T-0.......................................... 339 07-037 OPERATION SUPPORT SETUP 4 - LCC2 PAYLOAD SUPPORT CONFIGURATION........................ 343 07-047 OPERATION SUPPORT SETUP 5 - PRSD LO2 TANKER PLACEMENT.................................... 345 07-054 OPERATION SUPPORT SETUP 6 - PRSD LH2 TANKER PLACEMENT.................................... 347 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 08-000 OPERATION SUPPORT SETUPS - ORBITER............ 349 08-001 OPERATION SUPPORT SETUP 1 - MPS/ SSME MLP PATCH RACK - DISTRIBUTER PANEL INTEGRITY VERIFICATIONS................................ 349 08-008 OPERATION SUPPORT SETUP 2 - ORBITER STRUCTURAL PANEL CONFIG FOR ET TANKING AND LAUNCH........ 353 08-020 OPERATION SUPPORT SETUP 3 - ECLSS FES, NH3, O2/N2 PLUG SETS REMOVAL/ INSTALLATION........ 359 08-053 OPERATION SUPPORT SETUP 4 - GTOE HEADSET EQUIPMENT REMOVAL............................ 387 08-057 OPERATION SUPPORT SETUP 5 - VACUUM VENT LINE INERTING...................................... 389 08-074 OPERATION SUPPORT SETUP 6 - RPS INSTRUMENTATION LCC WORK AROUND SETUP - JRPS.. 399 08-078 OPERATION SUPPORT SETUP 7 - MEMORY COMPARE TAPE/FILE CHECK-IN............................ 403 08-085 OPERATION SUPPORT SETUP 8 - FCL CONFIGURATION RAD/BYPASS.................................... 407 08-104 OPERATION SUPPORT SETUP 9 - WINDOW COVER REMOVAL FOR FLIGHT............................ 413 08-112 OPERATION SUPPORT SETUP 10 - WASTE MANAGEMENT STATION INSPECTION/ CLOSEOUT SW - LIST........ 417 08-128 OPERATION SUPPORT SETUP 11 - GTOE HEADSET DELIVERY AND INSTALLATION.................... 425 08-139 OPERATION SUPPORT SETUP 12 - CREW COMPARTMENT FINAL CLEANING AND INSPECTION (OMTO).......... 431 08-140 OPERATION SUPPORT SETUP 12 - PART A - CREW COMPARTMENT FINAL CLEANING AND INSPECTION (OMTO)........................................ 431 08-164 OPERATION SUPPORT SETUP 12 - PART B - CREW MODULE FINAL INSPECTION...................... 439 08-167 OPERATION SUPPORT SETUP 13 - RPS TFL SETUP.... 441 08-171 OPERATION SUPPORT SETUP 14 - RPS MADS FDM/PCM TEST (ORBITER) - JRPS........................ 443 08-175 OPERATION SUPPORT SETUP 15 - RESERVED........ 447 08-176 OPERATION SUPPORT SETUP 16 - REMOVAL/IDENTIFICATION OF SWITCH GUARDS...... 449 08-182 OPERATION SUPPORT SETUP 17 - OMS/RCS ENGINE COVER INSTALLATION/RCS INSPECTIONS (CONTINGENCY)................................ 453 08-199 OPERATION SUPPORT SETUP 18 - SOUND SUPPRESSION/EMERGENCY EGRESS FLAME DETECTION MONITOR...................................... 463 08-216 OPERATION SUPPORT SETUP 19 - WHITEROOM INGRESS - EGRESS CONFIGURATION - CONTINGENCY.......... 469 08-220 OPERATION SUPPORT SETUP 20 - INGRESS/EGRESS HATCH CLOSING/LATCHING........................ 473 08-277 OPERATION SUPPORT SETUP 21 - OMS ENGINE COVERS AND THROAT PLUG REMOVAL...................... 491 08-289 OPERATION SUPPORT SETUP 22 - ORBITER AIRLOCK CLOSEOUT AND SEAL LEAK CHECK.................. 497 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 08-323 OPERATION SUPPORT SETUP 23 - RCS THRUSTER COVER CONFIG/GSE SECURING FOR LAUNCH.......... 511 08-420 OPERATION SUPPORT SETUP 24 - TFL/DFL (DPS).... 563 08-427 OPERATION SUPPORT SETUP 25 - APU EXHAUST DUCT PRESSURE PLUG/COVER REMOVAL AND WSB STEAM VENT CONFIGURATION................................ 565 08-438 OPERATION SUPPORT SETUP 26 - UNLOCK HATCH JETTISON "T" HANDLE BOX...................... 573 08-445 OPERATION SUPPORT SETUP 27 - HYDRAULIC WALKDOWN...................................... 575 08-449 OPERATION SUPPORT SETUP 28 - RESERVED........ 577 08-450 OPERATION SUPPORT SETUP 29 - MLP INTERIOR SECURING...................................... 579 09-000 OPERATION SUPPORT SETUPS - ET................ 581 09-001 OPERATION SUPPORT SETUP 1 - LH2 STORAGE TANK FILL - TANKERS................................ 581 10-000 OPERATION SUPPORT SETUPS - SRB................ 589 10-001 OPERATION SUPPORT SETUP 1 - SEAL SRB DRAIN HOLES........................................ 589 10-005 OPERATION SUPPORT SETUP 2 - OPEN SRB DRAIN HOLES (CONTINGENCY).......................... 595 10-009 OPERATION SUPPORT SETUP 3 - SRB APU BITE TEST AND SRB APU FUEL PUMP BEARING SEAL SOAK (T-27 HOURS)........................................ 599 10-041 OPERATION SUPPORT SETUP 4 - SRB APU BITE TEST AND SRB APU FUEL PUMP BEARING SEAL SOAK (T-9 HOURS)........................................ 609 10-071 OPERATION SUPPORT SETUP 5 - SRB AFT SKIRT GN2 PURGE ACTIVATION.............................. 617 11-000 OPERATION SUPPORT SETUPS - INTEGRATED........ 623 11-001 OPERATION SUPPORT SETUP 1 - SAFETY/ FACILITY/FIRE WALKDOWN........................ 623 11-022 OPERATION SUPPORT SETUP 2 - INITIAL TPS ENGINEERING DEBRIS WALKDOWN.................. 631 11-028 OPERATION SUPPORT SETUP 3 - FINAL TPS ENGINEERING DEBRIS WALKDOWN.................. 633 11-034 OPERATION SUPPORT SETUP 4 - EMERGENCY EGRESS ROUTE WALKDOWN................................ 637 11-043 OPERATION SUPPORT SETUP 5 - ET LOAD SAFETY/FACILITY/FIRE/WALKDOWN................ 639 11-061 OPERATION SUPPORT SETUP 6 - BDA FINAL CLEAR OPS/SAFETY WALKDOWN.......................... 647 11-068 OPERATION SUPPORT SETUP 7 - APU RESERVICING INTEGRATED SAFETY/ FACILITY/OPERATIONS WALKDOWN...................................... 649 11-077 OPERATION SUPPORT SETUP 8 - PRSD DESERVICING SAFETY/FACILITY/FIRE WALKDOWN................ 653 12-000 OPERATION SUPPORT SETUPS - PAYLOADS.......... 657 12-001 OPERATION SUPPORT SETUP 1 - RESERVED.......... 657 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 SECTION IV - OPERATION INSTRUCTIONS NA SECTION V - POST OPERATION INSTRUCTIONS NA APPENDICES A THRU Y .............................................. NA Z EMERGENCY INSTRUCTIONS ....................... 659 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 OR/OD 20007S LI OPERATIONS REQUIREMENTS/OPERATIONS DIRECTIVE - LLS (KSC) OR/OD 2XX00 LI OPERATIONS REQUIREMENTS/OPERATIONS DIRECTIVE - LLP (KSC) D3012 LI INTER-CENTER END-TO-END COMM CHECK (USA) 1.1.3 SUPPORTING SUBTASKS -1| | SUBTASK SUBTASK TITLE/ CALLING | NUMBER FUNCTION TO BE PERFORMED SEQ-STEP| ------- -------------------------- --------| | M3054 GN2 ENVIR/CAMERA LENS PURGE SYS 01-058 | | M3176 GN2 ENVIRON/CAM LENS PURGE SYS, PAD B 01-058 | | Q3018 PRE-LAUNCH, POST-LAUNCH, POST-FRF | INSPECTION, ELEVATOR 01-058 | | M3006 HVAC SYS/PTCR/ECS ROOM, PAD A, C-39 | REMOTE 01-065 | | M3023 PTCR/ECS RM. HVAC SYS, PAD B | REMOTE 01-065 | | M3088 LOW-LEVEL OXYGEN ANALYZER UNITS | OPERATION 01-071 | | M3054 GN2 ENVIR/CAMERA LENS PURGE SYS 01-076 | | M3176 GN2 ENVIRON/CAM LENS PURGE SYS, PAD B 01-076 | | M3189.001 SOUND SUPPRESSION LAUNCH COUNTDOWN | OPERATIONS 01-077 | | M3190 FIREX AND POTABLE WATER LAUNCH | COUNTDOWN OPERATIONS 01-078 | 01-079 | | M3189.001 SOUND SUPPRESSION LAUNCH COUNTDOWN | OPERATIONS 01-080 | | M3175 OPERATION OF HOLDING TANK INDUSTRIAL | WASTEWATER SYSTEM 01-082 | | M3083 MLP COMPOSITE STRUCTURE | BELLY BANDS 01-089 | | M3020 HIGH-PRESSURE GASEOUS HYDROGEN | FACILITY | MAINTAINING PAD GH2 SYSTEM 01-094 | 9 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 M3022 COMPRESSED AIR SYSTEM -1| SPECIAL CHECKOUT INSTRUCTIONS 01-094 | | M3054 GN2 ENVIR/CAMERA LENS PURGE SYS 01-094 | | M3067 CABIN AIR(OXYGEN/NITROGEN) | DISTRIBUTION SYSTEM | BREATHING AIR CABIN AIR FOR TEST | SUPPORT WITH TUBEBANK 01-094 | | M3097 HIGH PURITY GASEOUS OXYGEN SYSTEM | MAINTAINING PAD GO2 SYSTEM 01-094 | | M3176 GN2 ENVIRON/CAM LENS PURGE SYS, PAD B 01-094 | | M3197 HP GN2/GHE/COMP AIR/LPGN2 PREP, FRF | MLP GN2 GHE LPGN2 SYSTEM PREPARATION | FOR LAUNCH FRF TANKING TEST 01-094 | | A2700 GROUND SUPPORT COMM SYS VALID | VALIDATION OF COUNTDOWN TRANSMITTING | SUBSYSTEM TO JSC AND MFSC 01-097 | VALIDATION OF COUNTDOWN TRANSMITTING | SUBSYSTEM TO JSC AND MFSC 01-097 | LAUNCH STATUS CLOCKS HOLD TIME | REMAINING INTERFACE TEST, ON OIS | CHANNEL 178. 01-115 | | V1122 PAD A/B ECS SUPPORT OPERATIONS (LPS | AND LPC) | CONTROL STATION TRANSFER - FIRING | ROOM TO PAD 01-126 | CONTROL STATION TRANSFER - PAD TO | FIRING ROOM 01-159 | | C2000 LCC CCMS OPERATION SUPPORT 01-173 | | C3041 CCMS OPERATION SUPPORT PATCHING 01-174 | | C2000 LCC CCMS OPERATION SUPPORT 01-177 | | D3008 PURGE/PRESSURIZATION AND LOCKOUT | PROCEDURES FOR COMM ENCLOSURES 01-182 | 01-183 | 10 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 M3184 SOLID ROCKET BOOSTER SIDE FLAME -1| DEFLECTOR 01-211 | 01-216 | | M3189.001 SOUND SUPPRESSION LAUNCH COUNTDOWN | OPERATIONS | J 01-216 | 01-222 | 01-225 | | M3083 MLP COMPOSITE STRUCTURE 01-228 | | M3190 FIREX AND POTABLE WATER LAUNCH | COUNTDOWN OPERATIONS 01-232 | 01-239 | | C2000 LCC CCMS OPERATION SUPPORT 01-248 | | V1047 HATCH SEAL LEAKAGE TESTS 02-017 | | S9001VL2 SHUTTLE POWER UP/POWER DOWN (LPS) 02-037 | | V3600 GROUND COOLING SYSTEM OPERATIONS 02-041 | | S9001VL2 SHUTTLE POWER UP/POWER DOWN (LPS) 02-042 | | V66-50009 INSTALLATION/REMOVAL AIRLOCK OUT | VERTICAL ACCESS SET - CREW MODULE 02-045 | | V66-90006 PLATFORM ACCESS SET, A70-0558 MIDDECK, | CREW MODULE VERTICAL, REMOVAL 02-045 | | V5097.003 CREW SYSTEMS STOWAGE - FLIGHT | DECK/MIDDECK 02-046 | | V66-00009 PLATFORM ACCESS SET, A70-0558 MIDDECK, | CM, VERTICAL, INSTALLATION 02-047 | | V66-50009 INSTALLATION/REMOVAL AIRLOCK OUT | VERTICAL ACCESS SET - CREW MODULE 02-047 | | V3517 LH2 TSM PREPARATION TO SUPPORT | INTEGRATED TEST 02-051 | | V3518 LO2 TSM PREPARATION TO SUPPORT | INTEGRATED TEST 02-052 | | V1122 PAD A/B ECS SUPPORT OPERATIONS (LPS | AND LPC) 02-056 | | V5052 GSE HAZARD PROOFING 02-078 | 11 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 V1117 COMMUNICATIONS LAUNCH CONFIGURATION -1| CHECKOUT (LPS) 02-082 | | V33-90011 CREW MODULE WINDOW HARD COVER REMOVAL | AND PLUG INSTALLATION 02-083 | | V33-00005 CREW MODULE SOFT WINDOW COVER | INSTALLATION (EXTERIOR) 02-091 | | V33-00003 CREW MODULE WINDOW HARD COVER | INSTALLATION 02-092 | | V1117 COMMUNICATIONS LAUNCH CONFIGURATION | CHECKOUT (LPS) 02-095 | | V80-05901 DOOR 59-01, LH OMS/RCS PROPELLANT | SERVICE REMOVAL 02-101 | | V80-05902 DOOR 59-02, OMS/RCS RH PROPELLANT | SERVICE, REMOVAL 02-102 | | V80-95901 DOOR 59-01, LH OMS/RCS PROPELLENT | SERVICE, INSTALLATION 02-114 | | V80-95902 DOOR 59-02, OMS/RCS RH PROPELLENT | SERVICE, INSTALLATION 02-115 | | V1117 COMMUNICATIONS LAUNCH CONFIGURATION | CHECKOUT (LPS) 02-119 | | V1040.002 PRSD CRYO LOAD AND FUEL CELL | ACTIVATION 02-125 | | V1040.003 FUEL CELL PRSD LAUNCH | HOLD/RECYCLE/SCRUB CONTINGENCY | OPERATIONS | GO2 SAMPLE BOTTLE CONNECTION OMBUU 02-126 | GO2 SAMPLE BOTTLE CONNECTION OMBUU 02-126 | | V33-00012 MCDS OTV CAMERA/BRACKET AND OIS UNITS | REMOVAL 02-141 | | V5067 CREW MODULE AND AIRLOCK HATCH OPENING | AND CLOSING | A 02-143 | | V66-00019 PLATFORM ACCESS SET A70-0558 AFT | FLIGHT DECK INSTALLATION/REMOVAL 02-144 | 12 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 V66-50009 INSTALLATION/REMOVAL AIRLOCK OUT -1| VERTICAL ACCESS SET - CREW MODULE 02-144 | | V66-90006 PLATFORM ACCESS SET, A70-0558 MIDDECK, | CREW MODULE VERTICAL, REMOVAL 02-144 | 02-144 | | V5097.002 CREW SYSTEMS STOWAGE - WASTE | MANAGEMENT COMPARTMENT 02-147 | | V5097.001 CREW SYSTEMS STOWAGE - AIRLOCK 02-151 | | V5097.003 CREW SYSTEMS STOWAGE - FLIGHT | DECK/MIDDECK 02-154 | | T5401 H2 LEAK DETECTION EQUIPMENT | INSTALLATION (LD 54 AND LD 55) 03-011 | | G6205 LH2 SYSTEM MLP UTILITY SUPPORT | OPERATIONS 03-065 | 03-075 | | B5306 SRB ORDNANCE CONNECTION AND PAD | CLOSEOUT 04-012 | | V2274 ORBITER/SRB ESP PLATFORM TRANSPORTER | OPERATIONS 04-023 | | Q3208 FORKLIFTS, 2,000 POUNDS TO 30,000 | POUNDS 04-041 | | C2000 LCC CCMS OPERATION SUPPORT 07-014 | 07-015 | | C3041 CCMS OPERATION SUPPORT PATCHING 07-016 | 07-017 | | C2000 LCC CCMS OPERATION SUPPORT 07-024 | 07-039 | | C3041 CCMS OPERATION SUPPORT PATCHING 07-041 | | V3550 ROUTINE LH2 AND LOX TSM OPERATIONS 08-022 | 13 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 V1045VL10 OMS/RCS GLS ABORT TURNAROUND -1| CONTINGENCY (LPS) 08-190 | 08-192 | 08-194 | 08-196 | | V1047 HATCH SEAL LEAKAGE TESTS 08-260 | 08-261 | | V6029.003 OMS/RCS THRUSTER DESICCANT INSPECTION | AND REPLACEMENT 08-283 | | V66-50008 INSTALLATION/REMOVAL EXTERNAL AIRLOCK | PLATFORMS, LADDER - AIRLOCK 08-313 | | V66-90005 PLATFORM ACCESS SET A70-0558 AIRLOCK | SET CM, VERTICAL, REMOVAL 08-313 | | V5067 CREW MODULE AND AIRLOCK HATCH OPENING | AND CLOSING 08-318 | | V1047 HATCH SEAL LEAKAGE TESTS 08-321 | | G3255 LH2 SYSTEM SCRUB-TURNAROUND 09-002 | 09-021 | 09-031 | 14 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 1.2 COMPUTER SYSTEMS -1| ---------------- DPS CCMS SDC | RPS CCS 1.2.1 SYSTEM CONFIGURATION -------------------- A. CCMS ---- GSE LINKS OCTAL ADDRESS ------------- LINK FEP LOCATION HIMS PAD A PAD B ---- --- -------- ---- ----- ------- 1/21 GS1A/S PTCR 5980 022 151 5982 010 161 5983 211 166 5985 013 202 5986 020 206 5976 255 205 6377 165 365 2/22 GS3A/S PTCR 5984 212 173 RSS 6396 222 275 6397 023 303 6398 032 311 6399 233 316 FUEL AREA 8020 224 320 OXID AREA 8022 025 325 LCC 5512 167 170 3/23 GS2A/S PTCR 5981 235 155 5987 221 213 5988 230 217 5989 031 227 5996 026 246 5997 034 256 5977 305 204 6378 257 357 15 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 OCTAL ADDRESS ------------- LINK FEP LOCATION HIMS MLP ---- --- -------- ---- --- 4/24 GS1A/S MLP-7A 6852 201 6891 043 6894 040 6895 241 6896 242 6880 056 6860 276 5/25 GS2A/S MLP-7A 6893 253 6898 051 6861 312 6691 153 28/29 GS3A/S MLP-7A 6851 046 6897 250 6899 052 6689 116 VEHICLE DATA: ------------- LINK FEP FREQ ---- --- ---- OI OIA/S 128 KBS 192 KBS GPCA/S 128 KBS 192 KBS VSB 128 KBS 192 KBS PLDA/S 128 KBPS 192 KBPS EIU-1 ME1 60 KBS EIU-2 ME2 60 KBS EIU-3 ME3 60 KBS LDB LDBA-LDBS N/A LDBD (AS NEEDED) UPLINK UPLK 72 KBS 16 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 CONSOLES REQUIRED: ------------------ LCC1/LCC3 --------- C1 THRU C12, MSTR, INTG, BKUP, HSP2, BIOMED, PDR/SPA, LDBM, PP1, PP2 LCC2 ---- 3 PERSONNEL ACCOUNTABILITY CONSOLES 10 STS/TPS ICE/FROST DEBRIS SYSTEM CONSOLES ESA MONITORS/HOT SPARES (AS AVAILABLE) B. CDS/SDC ------- RTIF/DRD C. RPS -1| --- LINK ELEMENT ---- ------- 128 KBS OI ORB 64 KBS OI ORB 60 KBS EIU (3) SSME FDM1 (1-4) ORB FDM2 (1-4) ORB BMU (1-4) ORB MADS PCM ORB 32/64 KB | KMTS ME1 60KBS | ME2 60KBS | ME3 60KBS | OI 128/192 KBS | | MER (JSC) CCP 772KBS | 17 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 D. CCS EQUIPMENT ------------- OCTAL ADDRESS LINK FEP LOCATION HIMS PAD A PAD B ---- --- -------- ---- ------------- 11 GS1A PTCR 5990 030 122 PTCR 5991 231 125 PTCR 5992 232 130 CCS 0119 042 LCC 0120 243 CCF 8249 044 CCS 0118 226 UAX 7468 041 UAX 7469 245 12 GS2A C5 8390 254 VABR 7498 050 VABR 7499 251 13 GS3A PTCR 5993 033 133 PTCR 5994 036 142 PTCR 5995 237 145 MLP1,2,3 6892 234 066 350 CONSOLES -------- C1, C2, C3, INTG, MSTR 1.2.2 DATA REQUIREMENTS (REAL TIME) ----------------------------- PER OMI S9002VL16 INTEGRATED DATA REQUIREMENTS 1.2.3 DATA REQUIREMENTS (POST TEST) ----------------------------- PER OMI S9002VL16 INTEGRATED DATA REQUIREMENTS 18 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 1.4.9 VEHICLES, GROUND SUPPORT EQUIPMENT AND SPECIAL EQUIPMENT -1| ITEM LOCATION QTY ---- -------- --- RAIN SUITS PAD GATE A/R (CONTINGENCY) ACIDIC DEPOSIT PROTECTION RUBBERIZED SUITS, GLOVES, GOGGLES, AND SURGICAL FACE MASKS ARMORED VEHICLE SLIDEWIRE BUNKER 1 EA ARMORED VEHICLE A/B-5 RB (PAD A LAUNCH) 2 EA ARMORED VEHICLE A/B-4 RB (PAD B LAUNCH) 2 EA 140 TON (MIN) CRANE (LFAC) 1. SCAPE (JBOSC): A. 5 X 5 CAT I SCAPE FOR RED CREW CONTINGENCY IN MIDFIELD FALLBACK SCAPE TRAILER B. 1 600 LITER LIQUID AIR CARTS AT LC-39 OPERATIONAL SCAPE AREA C. 2 SCAPE TRAILERS AT OPERATIONAL SCAPE AREA (PAD-A ONLY) D. 2 CONTROL TRAILERS AT OPERATIONAL SCAPE AREA (PAD-A ONLY) E. 1 SUIT STORAGE TRAILER AT OPERATIONAL SCAPE AREA (PAD-A ONLY) F. SCAPE COMPLEX (PAD-B ONLY) 2. ONE INDUSTRIAL FIRST AID KIT IN SLIDEWIRE BUNKER. (PROVIDED BY NASA BIO/MED/CBSE) 3. AN/TVS-3 20KW XENON SEARCHLIGHTS (39) FOR PHOTO LIGHTING (SGS) | 4. 69 KW/400 HZ DIESEL GENERATORS (21) FOR XENON LIGHTS (SGS) | 59 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 5. PRIME MOVERS (ESP TRANSPORTER MOVE) 6. ELSA'S (JBOSC) -1| 1. 18 TO CCF39 2. 6 TO BLDG J8-2009 RM114 FOR PAD A LAUNCH AND J7-688 RM114 FOR PAD B LAUNCH. 3. 40 TO PSTM AT COMPLEX J, 40 TO PAD GATE POST LAUNCH 4. POSITIONED AT PAD (473 PAD A) (474 PAD B) 5. 130 POSITIONED IN MLP. 6. 15 TO ASTRONAUT CREW VAN (K6-1996) 7. 10 TO E/H BLDG L7-1557 8. 12 IN ENVIRONMENTAL CHAMBER (WHITE ROOM) 195 FT LVL 9. 25 TO PRESS SITE K7-1205F (SFOC CTVO) 10. 48 TO CCAS BLDG 1605 | 11. DELETED | 12. 10 TO TRM-006 (FOR CSR-4184B PERSONNEL) 13. 13 TO ECS ROOM (OMI V1122VL1 FOR PAD A/OMI V1122VL2 FOR PAD B) 14. 12 TO LCC, RM 1P4A 15. 10 TO WX'B' J6-553 16. 6 TO RADAR SITE 19.17 17. 14 TO K7-569 (SFOC PWR) | 18. 6 TO M5-1494 (S BAND) 19. 4 TO IFLOT BEACH ROAD PAD A K8-741 PAD B J8-1821 20. 15 TO ELSA LOCKERS (FSS 195 FT LVL) 21. 8 IN SLIDEWIRE BUNKER 22. 8 IN BUNKER ARMORED VEHICLE 23. 8 AT FIRE STA 2 (TO BE PLACED IN FSS ELEVATOR BY CLOSEOUT CREW) 25. 5 TO M6-342 RM 338 (NASA PHOTO COORD) 7. PORTABLE AIR VENTILATORS (JBOSC) 1. (1 PER FLT CREW +1) TO O&C 2. (1 PER FLT CREW) TO FS NO. 2 3. REMAINDER OF PAV'S TO SLIDEWIRE BUNKER 8. ARAP'S W/MANIFOLD ADAPTER HOSES ATTACHED (1 PER FLIGHT CREW MEMBER) POSITIONED IN ARMORED VEHICLE AT SLIDEWIRE BUNKER. 9. PORTABLE OXYGEN RESUSCITATORS TO M6-495, OHF (1) 10. ROPES, STANCHIONS, BARRIERS AND WARNING SIGNS 60 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 5. COUNTDOWN CLOCK MANAGEMENT -1| THE NTD IS RESPONSIBLE FOR MANAGEMENT OF THE COUNTDOWN CLOCK AND IMPLEMENTATION OF THE ASSOCIATED LAUNCH WINDOW CONSTRAINTS. LAUNCH WINDOW CONSTRAINTS ARE MANAGED BY THE NTD WITH THE AID OF A "CLOCK MANAGEMENT TOOL." THIS LAPTOP TOOL IS RESIDENT AT THE NTD CONSOLE WITH A BACKUP AT THE GLS CONSOLE. THIS TOOL ALLOWS THE NTD TO EFFECTIVELY INTEGRATE ALL LAUNCH CONSTRAINTS, CALCULATE THE LIMITING LAUNCH CONSTRAINT, AND DETERMINE THE LATEST RESUME TIMES FOR EACH GLS HOLD MILESTONE. THE APPLICABLE LAUNCH WINDOW CONSTRAINTS ARE AS LISTED: LAUNCH WINDOW - THE LAUNCH WINDOW IS DETERMIND EACH MISSION BY MOD AND COMMUNICATED TO THE NTD VIA THE FLIGHT DIRECTOR. THE INITIAL LAUNCH WINDOW INFORMATION UPDATE IS PROVIDE TO THE NTD VIA THE FLIGHT DIRECTOR AT T-55 MINUTES (L-1 HOUR 30 MINUTES). | DETERMINATION WHETHER TO TARGET THE WINDOW OPEN TIME OR THE "PREFERRED" LAUNCH TIME IS MADE BEFORE RESUMING THE COUNT AT T-9 MINUTES (L-37 MINUTES). AFTER THIS DETERMINATION, THE T-9 MINUTE HOLD LENGTH IS ADJUSTED TO SYNCHRONIZE THE CLOCK WITH THE CHOSEN | T-0. LAUNCH WINDOW PANES - THE PERIOD OF TIME AVAILABLE IN THE LAUNCH WINDOW CORRESPONDING TO A FLIGHT DAY 3 RENDEZVOUS CONSTITUTES A SINGLE PANE IN THE WINDOW. IF A FLIGHT DAY 4 RENDEZVOUS IS ACHIEVABLE FOR A PARTICULAR MISSION, WITH WINDOW WILL BE COMPOSED OF A SECOND PANE. FOR A 2 PANE MISSION, THERE MAY BE A PERIOD WITHIN THE LAUNCH WINDOW WHERE THE ON-BOARD PASS AND BFS SOFTWARE MUST BE SYNCHRONIZED TO ACCOMMODATE A FLIGHT DAY 4 RENDEZVOUS INSTEAD OF THE PLANNED FLIGHT DAY 3 RENDEZVOUS. THE PANE SWAP IN THE SOFTWARE IS PROTECTED BY A 10-SECOND CUTOUT IN THE WINDOW KNOWN AS THE PANE SWAP CUTOUT. THE FLIGHT DIRECTOR PASSES THE PANE SWAP TIME TO THE NTD WITH OTHER PERTINENT WINDOW INFORMATION. THE NTD ENSURES THAT A LAUNCH DOES NOT OCCUR DURING THIS TIME PERIOD. 73 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 COLLISION AVOIDANCE TIMEFRAMES (COLA) - A LAUNCH -1| CANNOT OCCUR DURING A PERIOD WHERE THE ORBITAL TRAJECTORY WILL CARRY THE VEHICLE WITHIN A SPECIFIED RANGE OF ANOTHER MANNED SPACECRAFT. A COLA IS CALCULATED BY THE EASTERN RANGE AND PASSED | TO THE NTD TO PROTECT AGAINST LAUNCHING DURING SUCH A TIME. THE NTD ENSURES THAT A LAUNCH DOES NOT OCCUR DURING THESE TIME PERIODS. LOX DRAINBACK PERFORMANCE HOLD TIME - PERFORMANCE HOLD TIME AVAILABLE AFTER THE START OF LOX DRAINBACK IS COMPUTED BY MOD BASED ON THE LSEAT ASSESSMENT OF PROPELLANT LOAD AND GIVEN TO THE NTD VIA THE FLIGHT DIRECTOR DURING THE T-9 MINUTE HOLD (L-37 MINUTES.) THIS TIME MUST BE UPDATED AT T-4:55 MINUTES IF THE T-9 MINUTE HOLD IS EXTENDED OR IF THERE ARE ANY HOLDS BETWEEN T-9 AND T-5 MINUTES. SSME LO2 INLET TEMPERATURE LIMIT (START BOX TEMP LIMIT) THE HOLD TIME AVAILABLE AFTER START OF LO2 DRAINBACK AND BEFORE VIOLATION OF THE SSME INLET TEMPERATURE LIMIT IS PREDICTED IN THE OMRSD WITH THE ACTUAL CRITERIA DEFINED IN LCC MPS-25 AND CODED IN THE GLS. THE SPE REPORTS THIS CONSTRAINT VALUE TO THE NTD IN THE T-20 MINUTE HOLD. GOX ULLAGE PRESSURE GENERIC CERTIFICATION ANALYSIS- THE HOLD TIME AVAILABLE AFTER THE START OF LO2 DRAINBACK WILL NOT EXCEED 5.0 MINUTES FOR SLWT ET'S WITH ANY ORBITER, 6.0 MINUTES FOR LWT ET'S WITH OV-102, OR 6.7 MINUTES FOR LWT ET'S WITH OV-103, 104 OR 105. THIS DETERMINATION IS MADE AND RECORDED IN S1003. THE LOX SYSTEM ENGINEER (CLOX) REPORTS THE CONSTRAINT VALUE TO THE NTD IN THE T-20 MINUTE HOLD. 74 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 FUEL CELLS AND PRSD ------------------- 14. CFCP, WITH SFOC SAFETY CONCURRENCE, MAY PERFORM FUEL CELL 8 HR OPERATIONAL PURGE AS REQUIRED TO MAINTAIN FUEL CELL PERFORMANCE. SEQUENCES OR STEPS IN THIS OMI THAT CALL OUT DATA RECORDINGS FOR PRSD O2/H2 TANK SETS NOT INSTALLED IN THE VEHICLE SHALL HAVE N/A RECORDED ON DATA LINE. 15. STEPS WITHIN SCRUB SEQUENCES WILL NOT NECESSARILY BE WORKED IN ORDER. SCRUB BAR CHARTS AND TEST TEAM REALTIME REQUIREMENTS WILL DETERMINE SEQUENCING OF EVENTS. (VOL 3) IF PRSD DESERVICING, RESERVICING, TOPOFF, AND/OR CATHODE ACTIVATION IS REQUIRED DURING SEQ 32 - 48 HR OR LONGER SCRUB, THEY WILL BE INITIATED BY SEQUENCE 32 THEN RUN BY SEQ 36. PRSD OPTIONS WILL BE RUN IN PARALLEL WITH SEQ 32. (VOL 3) MISCELLANEOUS ------------- 16. FLIGHT CREW MAY PERFORM MCDS KEYBOARD ENTRIES AT THEIR DISCRETION. 17. IF IT BECOMES NECESSARY TO RUN SEQUENCES OR PART OF A SEQUENCE MORE THAN ONCE, QUALITY WILL MAKE A COPY OF THE ORIGINAL, LABEL IT RUN XX AND USE THE COPY FOR BUY OFF PURPOSES. 18. THE PAYLOAD PROCEDURE SUPPLEMENT - STS-XXX PAGES/ SEQUENCES WILL BE REPLACED EACH MISSION, AND CAN BE RE-RUN FOR EACH LAUNCH ATTEMPT. 19. TPS VITT XXXX MISSION UNIQUE CREW COMPARTMENT CONFIGURATION IS TO BE CONSIDERED AS A SUBTASK AND VERIFIED BY THIS OMI. TPS NUMBER WILL BE ASSIGNED EACH FLOW. TPS WILL NOT BE ENTERED ON THE CONSTRAINTS LIST. 20. VERBAL QUICK-LOOK DAMAGE ASSESSMENT REPORTS ARE DUE TO PAD MANAGER FROM EACH NASA/CONTRACTOR LEAD STARTING ONE HOUR AFTER PAD ENTRY. 21. LAUNCH DANGER AREA (LDA) MANLOADING REQUIREMENTS ARE CONTROLLED AND VERIFIED BY THIS OMI. LDA BADGE ISSUANCE AND CHANGES TO FIGURE 7 - LDA MANLOADING CHART WILL BE COORDINATED THROUGH PZ-A3 BY OMI DEVIATION. 77 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 1.8 OMRS REQUIREMENTS SATISFIED BY THIS TOP -1 --------------------------------------- VEHICLE/ELEMENT NO. ORB_____/FLT_____ ET_____ SRB_____ LH___ RH___ GROUND HARDWARE PMN/SN _________ COMPONENT/SEGMENT ___________/FLT_____ SITE ______ TCN _______________ DATE ___________ TOP WAS RUN AS A STANDALONE YES _____ NO _____ TOP WAS RUN AS A SUBTASK TO TOP _________________. NOMENCLATURE/ SEQ-STEP QC/ENG OMRS NO./CIL NO EFFECTIVITY (CAP) VERIF --------------- ------------- -------- ----- | B08SB0.070-B AFT SKT F/T DRAIN HOLE INSP AT PAD 10-003 _____| B011-999 | | B42FSC.011 HYDRAZINE TEMPERATURE CONTROL 10-085 _____| BAF;C | | G51FFH000.004 CHEMICAL SAMPLING-LH2 07-058 _____| GOF1-90;C (PAD-A) | | G51FF0000.015 CHEMICAL SAMPLING-LO2 07-052 _____| GOF1-90;C (PAD-A) | | G61FFH000.004 CHEMICAL SAMPLING-LH2 07-058 _____| GOF1-90;C (PAD-B) | | G61FF0000.015 CHEMICAL SAMPLING-LO2 07-052 _____| GOF1-90;C (PAD-B) | | P018DB.010 PRELAUNCH PAYLOAD BAY PURGE 08-175A _____| PAXAF | 08-175D _____| | P330DB.100 PRELAUNCH GROUND PURGE 08-175A _____| PAXAF (AXAF) | | 08-175D _____| (AXAF) | 78 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 1.8 OMRS REQUIREMENTS SATISFIED BY THIS TOP -1 --------------------------------------- VEHICLE/ELEMENT NO. ORB_____/FLT_____ ET_____ SRB_____ LH___ RH___ GROUND HARDWARE PMN/SN _________ COMPONENT/SEGMENT ___________/FLT_____ SITE ______ TCN _______________ DATE ___________ TOP WAS RUN AS A STANDALONE YES _____ NO _____ TOP WAS RUN AS A SUBTASK TO TOP _________________. NOMENCLATURE/ SEQ-STEP QC/ENG OMRS NO./CIL NO EFFECTIVITY (CAP) VERIF --------------- ------------- -------- ----- S00FA0.560 WSB STEAM VENT CONFIG FOR LAUNCH 08-435 _____| (1R ) VAF1-90 | | S00FA0.776 RSRM NOZZLE FLEX BEARING TEMP LIMIT 10-085 _____| (1 ) L04 B068-999 | | S00FA0.777 RSRM NOZZLE TO CASE TEMPERATURE LIMIT 10-085 _____| (1R ) L02 B062-999 | | S00FA0.800 PRELAUNCH BLOWOUT PLUG INSP 04-012 _____| (1 ) B025,027-999 | | V00I00.020 ET CRYO TANKING 08-016 _____| VAF1-90 | | V00I00.030 ORB CONFIG FOR LAUNCH 08-018 _____| VAF1-90 | | V05AD0.010-A SIDE/OVERHEAD OUTER WINDOW 02-086 _____| VAF1-90 | | V05AD0.010-B SIDE HATCH INNER WINDOW CAVITY 08-232 _____| VAF1-90 | | V05AD0.010-C SIDE HATCH OUTER WINDOW CAVITY 08-232 _____| VAF1-90 | 79 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 1.8 OMRS REQUIREMENTS SATISFIED BY THIS TOP -1 --------------------------------------- VEHICLE/ELEMENT NO. ORB_____/FLT_____ ET_____ SRB_____ LH___ RH___ GROUND HARDWARE PMN/SN _________ COMPONENT/SEGMENT ___________/FLT_____ SITE ______ TCN _______________ DATE ___________ TOP WAS RUN AS A STANDALONE YES _____ NO _____ TOP WAS RUN AS A SUBTASK TO TOP _________________. NOMENCLATURE/ SEQ-STEP QC/ENG OMRS NO./CIL NO EFFECTIVITY (CAP) VERIF --------------- ------------- -------- ----- V09AG0.020 WINDOW CLEANING/INSPECTION 02-090 _____| (1 ) L03 V02F19-90 | V03F22-90 02-093 _____| V04F15-90 | V05F9-90 08-109 _____| | V09AH0.100 RSI - ORB ACCESS ARM INTERFACE INSP 08-273 _____| (1 ) L03 V02F21-90 | V03F22-90 | V04F18-90 | V05F12-90 | | V33AH0.010 I/E HATCH CLOSE & LATCH FOR FLT-VERT 08-256 _____| L03 V02F22-90 | V03F23-90 | V04F19-90 | V05F12-90 | | V33AH0.110 I/E HATCH SEAL LEAK CHECK FOR FLT 08-260 _____| (1R ) V02F22-90 | V03F23-90 08-261 _____| V04F19-90 | V05F12-90 | | V42BE0.010-A LEFT POD LAUNCH COVERS 08-372 _____| L02 LP01F24-25 | LP03F19-20 | LP04F16-18 | LP05F7-8 | LEFT POD LAUNCH COVERS | L03 LP01F26-90 | LP03F21-90 | LP04F19-90 | LP05F9-90 | 80 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 1.8 OMRS REQUIREMENTS SATISFIED BY THIS TOP -1 --------------------------------------- VEHICLE/ELEMENT NO. ORB_____/FLT_____ ET_____ SRB_____ LH___ RH___ GROUND HARDWARE PMN/SN _________ COMPONENT/SEGMENT ___________/FLT_____ SITE ______ TCN _______________ DATE ___________ TOP WAS RUN AS A STANDALONE YES _____ NO _____ TOP WAS RUN AS A SUBTASK TO TOP _________________. NOMENCLATURE/ SEQ-STEP QC/ENG OMRS NO./CIL NO EFFECTIVITY (CAP) VERIF --------------- ------------- -------- ----- V42BE0.010-B RIGHT POD LAUNCH COVERS 08-372 _____| L02 RP01F22-23 | RP03F22-23 | RP04F15-16 | RP05F7-9 | RIGHT POD LAUNCH COVERS | L03 RP01F24-90 | RP03F24-90 | RP04F17-90 | RP05F10-90 | | V42BE0.010-C FRCS LAUNCH COVERS 08-372 _____| L02 FR02F18-19 | FR03F21-22 | FR04F15-16 | FR05F9-11 | FRCS LAUNCH COVERS | L03 FR02F20-90 | FR03F23-90 | FR04F17-90 | FR05F12-90 | | V63AR0.020 WATER INTRUSION INSPECTION 08-040 _____| VAF;C | | V63AR0.025 FES PLUGS FINAL REMOVAL 08-034 _____| L01 V02F20 | V04F17 | V05F11 | ATCS PLUGS FINAL REMOVAL | L02 V02F21-90 | V03F22-90 | V04F18-90 | V05F12-90 | 81 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 1.8 OMRS REQUIREMENTS SATISFIED BY THIS TOP -1 --------------------------------------- VEHICLE/ELEMENT NO. ORB_____/FLT_____ ET_____ SRB_____ LH___ RH___ GROUND HARDWARE PMN/SN _________ COMPONENT/SEGMENT ___________/FLT_____ SITE ______ TCN _______________ DATE ___________ TOP WAS RUN AS A STANDALONE YES _____ NO _____ TOP WAS RUN AS A SUBTASK TO TOP _________________. NOMENCLATURE/ SEQ-STEP QC/ENG OMRS NO./CIL NO EFFECTIVITY (CAP) VERIF --------------- ------------- -------- ----- V64AA0.080 AIRLOCK VACUUM VENT DUCT INERTING 08-072 _____| L01 V02FE20;C | V04FE17;C | V05FE11;C | AIRLOCK VACUUM VENT DUCT INERTING | L02 V02F21-90R21;C | V03F22-90R22;C | V04F18-90R18;C | V05F12-90R12;C | | V66AC0.170 EDO WCS CONSUMABLES INSTALLATION 08-120 _____| VAF;C | | V67AA0.020-A FLIGHT DECK CLEANLINESS 08-146 _____| L02 V02F16-90 | V03F18-90 | V04F13-90 | V05F6-90 | | V67AA0.020-B MIDDECK CLEANLINESS 08-157 _____| L02 V02F16-90 | V03F18-90 | V04F13-90 | V05F6-90 | | V72CA0.040-A MMU1 FLT SOFTWARE CONFIG FOR LCD 08-083 _____| V02F22-90 | V03F23-90 | V04F19-90 | V05F12-90 | 82 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 1.8 OMRS REQUIREMENTS SATISFIED BY THIS TOP -1 --------------------------------------- VEHICLE/ELEMENT NO. ORB_____/FLT_____ ET_____ SRB_____ LH___ RH___ GROUND HARDWARE PMN/SN _________ COMPONENT/SEGMENT ___________/FLT_____ SITE ______ TCN _______________ DATE ___________ TOP WAS RUN AS A STANDALONE YES _____ NO _____ TOP WAS RUN AS A SUBTASK TO TOP _________________. NOMENCLATURE/ SEQ-STEP QC/ENG OMRS NO./CIL NO EFFECTIVITY (CAP) VERIF --------------- ------------- -------- ----- V72CA0.040-B MMU2 FLT SOFTWARE CONFIG FOR LCD 08-083 _____| V02F22-90 | V03F23-90 | V04F19-90 | V05F12-90 | | V72CA0.045-A MMU 1 DUMP TRANSMISSION TO JSC/SPF 08-083 _____| V02F22-90 | V03F23-90 | V04F19-90 | V05F12-90 | | V72CA0.045-B MMU 2 DUMP TRANSMISSION TO JSC/SPF 08-083 _____| V02F22-90 | V03F23-90 | V04F19-90 | V05F12-90 | 82.1 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 THIS PAGE INTENTIONALLY BLANK 82.2 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ 01-027 JSTC JSEP VERIFY FOLLOWING GENERATORS ARE ELEC 114 AVAILABLE, VALIDATED AND READY TO -1| SUPPORT S0007: 1. PROVIDE 1 EA 2.5 KW, 1 PH 120/240 VOLT, 60HZ LIGHT BANK GENERATORS AT THE FOLLOWING LOCATIONS: A. ROADBLOCK A/B-23, KENNEDY PKWY AND SHARKEY RD. (WEST) B. ROADBLOCK A/B 38, KENNEDY PKWY AND TOW WAY (WEST) 2. PROVIDE GENERATOR WITH LIGHT BANK WITH OPERATOR TO K6-1145 (MFF) FROM L-3 HRS THRU LAUNCH TO SUPPORT TRIAGE VAN. 3. PROVIDE 15 KW, 3 PH, 120/208 VOLT, 60 HZ GENERATOR AT BAIR COVE FOR USCG SECURITY OPERATIONS. USCG WILL COORDINATE DELIVERY AND PICKUP. (T-1 DAY THRU LAUNCH). | 4. PROVIDE XENON LIGHTS AT LAUNCH PAD | AND BORESITE AS REQUIRED. | 93 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ 01-028 JSTC GSPN VERIFY FOLLOWING READY TO SUPPORT: PNU 114 1. HPGN2 AND HPGHE 4800-5660 SYSTEM, CCF, AND CCF-39 GN2 PRODUCTION PLANT (M3703, M3704, M3036). 2. LPGN2 INDUSTRIAL SUPPLY (M3703). 3. 28 VDC POWER, CONVERTER COMPRESSOR FACILITY (CCF) (M2023). 4. HP GN2/GHE VALVE POSITIONING PER 24 HR VALVE POSITION SEQ OF M3704. 5. CCF INDUSTRIAL PREPS (M3703). 6. ECS AIR/GN2 SUPPORT (M3703). 7. SUPPORT/CONNECT GN2 RECHARGER(S) TO FACILITY PIPING AT CCF INTERFACE. (M3704) 8. FALLBACK AREA SUPPORT, CCF. (T-6 HRS) (M3086) 9. TWO GHE COMPRESSORS ON 2 HR CALL PRIOR TO AND THROUGH LAUNCH COUNTDOWN. UNITS MUST BE AVAILABLE FOR HELIUM SUPPORT AT CCF WITHIN 2 HRS IF REQUESTED BY TEST CONDUCTOR. WHEN NOTIFIED, POSITION UNITS EAST OF CCF (M3036, Q3052). 94 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ 01-040 JSTC *SCB VERIFY FOLLOWING ELSA'S (10 MIN) DEPLOYED -1| NET AND READY TO SUPPORT THROUGH END OF MISSION 104 (EOM). 48 TO CCAS BLDG 1605 | L-7 DAYS. | 10 DELIVERED TO WX "B", J6-553. 5 TO BLDG 1605 (BIONETICS) T-1 DAY | 25 DELIVERED TO PRESS SITE K7-1205F (SFOC CTVO) 6 TO RADAR SITE 19.17. 10 DELIVERED TO TRM-006 SE CORNER FOR CSR TROUBLE CALLS TO CAMERA PADS. 14 DELIVERED TO K7-569 (SFOC SPECIAL POWER) | SOUTHEAST SIDE | 5 DELIVERED TO M6-342 RM 338 (NASA PHOTO COORD). 15 DELIVERED TO ASTRO-VAN AT K6-1996 (SFOC HEAVY EQUIPMENT) 101 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ 01-041 JSTC *SCB VERIFY FOLLOWING DEPLOYED AND READY LS NET TO SUPPORT: 104 1. EQUIPMENT/SERVICES TO FIRE STN NO. 2 AT T-06H30M A. 4 CAT I COMM CABLES B. 12 LAPS W/COMM (T-6HRS30M) 2. 2 EA LIQUID AIR PACKS (LAPS) TO LIFE SUPPORT AIR PACK VAN, COMPLEX J (T-4H00M). CONTINGENCY FOR CLOSEOUT CREW. 3. RESERVICE (TOP-OFF) 12 LAPS DELIVERED BY FIRE DEPT TO SLF MIDFIELD LIFE SUPPORT TRAILER BY T-3 HRS. 4. 5 LAPS WITHOUT COMM AND 3 LAPS WITH COMM TO FIRE STATION 2 AT T-4 HRS FOR CLOSEOUT CREW. 5. 16 LAPS WITH COMM TO FIRE STATION 2 AT T-4 HRS FOR FLIGHT CREW RESCUE TEAM. 6. SLIDEWIRE BUNKER (BUNKER SHELF) - ARAP'S WITH MANIFOLD ADAPTER HOSES ATTACHED. (1 EACH PER FLT CREW MEMBER) 7. DELIVER (FLIGHT CREW SIZE + 1) PORTABLE AIR VENTILATORS TO O&C CUL-DE-SAC, ASTRONAUT CREW VAN AT L-6 HRS PRIOR TO LAUNCH. 8. DELIVER (FLIGHT CREW SIZE) PORTABLE AIR VENTILATORS TO FIRE STATION NO. 2 AT L-7 HRS PRIOR TO LAUNCH FOR ASTRONAUT CLOSEOUT CREW. 9. DELIVER REMAINING PORTABLE AIR VENTILATORS TO PAD SLIDEWIRE BUNKER AT L-11H (T-8H30M). 102 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ 01-042 11. VERIFY BUNKER EQUIPPED WITH CON'T FOLLOWING B/A EQUIPMENT: A. 12 HOSES WITH LEH ADAPTERS ON EACH B. 12 ISI BREATHING AIR MASK PLACED ON SHELF 12. VERIFY 3 EA BREATHING AIR LINES WITH OIS-D COMM AND MASKS ON RIGHT AND LEFT SIDES READY FOR FINAL CLOSEOUTS ON 107 FT LVL, 120 FT LVL, 207 FT LVL OF RSS. 2 EA AIR LINES WITH COMM RIGHT AND LEFT ON '0' LEVEL MLP (HPU CLOSEOUTS). 13. REMOVE ELSA BOXES NOT EQUIPPED WITH HOLDDOWN CABLES AND ANY LOOSE EQUIPMENT ON RSS/FSS, MLP AND PAD SURFACES. 01-043 JSTC *SCB VERIFY PREPARED TO PERFORM/PROVIDE LS NET FOLLOWING: 104 1. PROVIDE 40 ELSA'S TO PSTM AT COMPLEX J T-6 HRS 30 MIN. (AIR PACK VAN) 2. PROVIDE 16, 30 MINUTE AIR PACKS, POSITION WITH VEHICLE AND DRIVER AT PAD ___ GATE T-9 HRS 30 MIN TO T-6 HOURS 30 MINUTES FOR ORB RED CREW AND RETURN TO COMPLEX J. 3. 5X5 CAT I SCAPE AT SLF MIDFIELD PARK SITE SCAPE TRLR FOR RED CREW CONTINGENCY (Q3187,Q2005) (T-6 HRS). 4. PROVIDE 40 ELSA'S TO PAD GATE POST LAUNCH. (AIR PACK VAN) 105 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ 01-044 JSTC JSDY VERIFY PREPARED TO INSTALL BLAST SHUTTERS MECH 114 ON WINDOWS FACING PAD ON EACH OF FOLLOWING TRAILERS LOCATED IN LOX AND LH2 AREAS: (INSTALL L-4 DAYS, SHUTTERS STORED IN EACH TRAILER) PAD-A LAUNCH: 1. TRLR-714 2. TRLR-434 3. TRLR-707 4. TRLR-435 5. TRLR-427 6. TRLR-428 7. TRLR-021 8. TRLR-025 NOT PERFORMED ______ PAD A PAD-B LAUNCH: 1. TRLR-486 2. TRLR-697 3. TRLR-698 4. TRLR-699 NOT PERFORMED ______ PAD B | 01-045 JSTC JSDY VERIFY PREPARED TO PERFORM FOLLOWING: -1| 114 1. VERIFY LOCOMOTIVE/RAIL CREWS HAVE BEEN | NOTIFIED THERE WILL BE NO LOCOMOTIVE/ | RAILCAR MOVEMENT WITHIN LDA FROM T-6 HRS, | ___ EST, TO T+1 HR, ___ EST. | | 2. MOVE SRM SEGMENT RAILCARS FROM BEACH | SIDING TO BALLOON SIDING L-2 DAYS, | IF REQUIRED. | NOT PERFORMED ______| SS2 | 106 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ 01-046 JSTC GSHE VERIFY PREPARED TO PERFORM/PROVIDE HEQ -1| NET GSUP FOLLOWING (7-4030/7-1808): LOG 102 1. PROVIDE FUEL TRUCK AND OPERATOR TO FUEL CRASH/RESCUE VEHICLES AND ARMORED VEHICLES AS REQUESTED BY FIRE SERVICES. PROVIDE FUEL TO FALLBACK VEHICLES AND ALL GENERATORS SUPPORTING S0007. 2. PROVIDE FALLBACK FUEL SUPPORT (T-6 HOURS). 3. SUPPORT FALLBACK SUPPORT (T-6HRS IN SHOP) HEQ MAINT. 106.1 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ THIS PAGE INTENTIONALLY BLANK 106.2 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ 03-033 PRE-OPERATION SETUP 5 - HWS REMOTE LEAK --------------------------------------- DETECTOR SYSTEM PRETEST VERIFICATIONS ------------------------------------- NOTE -1| THIS PRE-OPERATION SETUP IS NOT A CONSTRAINT TO CALL-TO-STATIONS. COMPLETION IS VERIFIED IN S0007VL2 (SEQ 14). THIS PRE-OPERATION SETUP WILL BE PERFORMED TO VERIFY VALIDATION OF REMOTE LEAK DETECTORS IN HELIUM ENVIRONMENT. THE HUMS WILL BE USED TO GATHER | BASELINE DATA ON VARIOUS HELIUM PURGES. EACH GROUP OF CABINETS HAVE THEIR OWN DEDICATED HELIUM PURGES; THEREFORE, CABINETS CAN BE VERIFIED INDEPENDENTLY REGARDLESS OF ORDER AND IN PARALLEL WITH EACH OTHER AT ENGINEER'S DISCRETION. THIS PRE-OPERATION SETUP WILL BE NOT PERFORMED AT ENGINEER'S DIRECTION ONLY. HWS LSO-SE CONCURRENCE _________________________ HWS NASA-SE CONCURRENCE _________________________ PRE-OPERATION SETUP 5 NOT PERFORMED ______ 263 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ 03-034 TBC CHGD PERFORM ET PRE-OPERATION SETUP 5 - HWS 136 REMOTE LEAK DETECTOR SYSTEM PRETEST VERIFICATIONS. 03-035 JHGD LCC 3R18 HUMS CONTROL ROOM - HUMS REMOTE TERMINAL START ARCHIVE FILE: "STSXXX_S0007_ET_POSU5" 6145 CABINET VERIFICATION ------------------------- 03-036 CHGD TBC VERIFY STATUS OF ET GUCP CAVITY HELIUM 136 PURGE (ON/OFF) AND STATUS OF T-0 GHE UMBILICAL TBC CLHY PURGE (ON/OFF). OBTAIN CLHY AND CMPS CMPS CONCURRENCE TO PROCEED WITH PURGE ACTIVATION. NOTE DO NOT PERFORM NEXT TWO STEPS IF ET GUCP CAVITY HELIUM PURGE ON. 03-037 CHGD TBC ATTENTION ON PAD ___ FSS: 136 TBC ET GUCP CAVITY WILL BE PURGED WITH HELIUM PA IN ONE MINUTE. NOT PERFORMED ______ NOTE WAIT ONE MINUTE MINIMUM. 03-038 CHGD PETG AFTER ONE MINUTE MINIMUM: 177 S72-0697-8 PANEL (215 FT LVL FSS) 1. VERIFY 750 PSI HE SUPPLY SHUTOFF VALVE A78376 OPEN. 2. VERIFY GAUGE SHUTOFF VALVE A78377 OPEN. 3. VERIFY 750 PSI HE SUPPLY PRESS GAUGE A78379 INDICATES 750 +/- 50 PSIG. 264 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ 6407 CABINET VERIFICATION ------------------------- NOTE DO NOT PERFORM NEXT THREE STEPS IF TSM T-0 UMBILICAL CAVITY HELIUM PURGE ON. 03-063 CHGD TBC NOTIFY OTC AND NTD LH2 T-O UMBILICAL GHE 136 PURGE TO BE ACTIVATED. TBC NTD 232 NTD OTC NOT PERFORMED ______ 03-064 TBC ATTENTION ON MLP ___: PA THE LH2 T-0 HELIUM UMBILICAL CARRIER PURGE IN THE LH2 TSM WILL BE ACTIVATED MOMENTARILY. NOT PERFORMED ______ 03-065 CHGD QMTG PERFORM LH2 T-0 UMBILICAL PURGE - S72-0685-2 -1| 177 PANEL PER OMI G6205 (SEQ 20) THROUGH PURGE ACTIVATION. REPORT COMPLETION. T:______ NOT PERFORMED ______ 273 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ 03-065A CHGD OTC RECORD THE CURRENT ORBITER VENT DOOR -1| 132 CONFIGURATION: | OTC PPVE | CTPE VENT DOOR 8 RIGHT __________ (OPEN,CLOSED,OR | PURGE) | VENT DOOR 8 LEFT __________ (OPEN,CLOSED,OR | PURGE) | | VENT DOOR 9 RIGHT __________ (OPEN,CLOSED,OR | PURGE) | VENT DOOR 9 LEFT __________ (OPEN,CLOSED,OR | PURGE) | | RECORD THE CURRENT PURGE RATES: | | PC2 PURGE RATE __________ BD | | PC3 PURGE RATE __________ BD | | RECORD CURRENT AFT CLOSE OUT FLIGHT | DOOR CONFIGURATION: | | AFT 50-1 DOOR __________ (INSTALLED OR NOT) | | AFT 50-2 DOOR __________ (INSTALLED OR NOT) | | 03-066 CHGD CURSOR CNTL (SAW01/HWW12) LD 28/32 PRI PUMP - ON LD 56/57 PRI PUMP - ON MFC POWER - ON SUPPORT MODE XMIT CURSOR KEY - PRESS 273.1 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ THIS PAGE INTENTIONALLY BLANK 273.2 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ 03-067 CHGD CURSOR CNTL (SAW01/HWW12) MANUAL SELECT SV1 - (CAL) SV2 - (CAL) SV3 - (CAL) SV4 - (CAL) XMIT CURSOR KEY - PRESS CRT RECORD AND VERIFY PRIMARY INDICATIONS LD28=__________PPM 0 +/- 6000 BD LD32=__________PPM 0 +/- 6000 BD LD56=__________PPM 0 +/- 6000 BD LD57=__________PPM 0 +/- 6000 BD MFC1=__________SLPM 2.8 +/- .5 BD MFC3=__________SLPM 2.8 +/- .5 BD MFC5=__________SLPM 2.8 +/- .5 BD MFC7=__________SLPM 2.8 +/- .5 BD SUPPORT MODE XMIT CURSOR KEY - PRESS NOTE ALLOW READINGS TO STABILIZE PRIOR TO RECORDING DATA. 03-068 CHGD RECORD LEAK DETECTOR INDICATIONS: LD PRIMARY -- ------- 28 __________ PPM BD 32 __________ PPM BD 56 __________ PPM BD 57 __________ PPM BD 274 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ 03-089 PRE-OPERATION SETUP 6 - PAD FIRE DETECTOR ----------------------------------------- ALIGNMENT --------- NOTE -1| THIS PRE-OPERATION SETUP IS NOT A CONSTRAINT TO CALL TO STATIONS. COMPLETION IS VERIFIED IN S0007VL2 (SEQ 14). DO NOT PERFORM PRE-OPERATION SETUP 6 IF PAD FIRE DETECTOR ALIGNMENT WAS PREVIOUSLY ACCOMPLISHED. | SHOP AIDE SA-059-024-501-001 OR | -002 IS USED IN THIS PRE-OPERATION | SETUP. THIS SHOP AIDE CONTAINS | A LASER DEVICE AND OPTICAL | ATTACHMENT; EITHER MAY BE USED | FOR FIRE DETECTOR ALIGNMENT. | PRE-OPERATION SETUP 6 NOT PERFORMED ______ 03-090 QHGD *PAD INSTALL ACCESS FOR FIRE PROTECTION HESD GBHE ALIGNMENT AT FOLLOWING PAD LOCATIONS: *PAD TBC 136 1. FSS 115 FT LEVEL SOUTHEAST CORNER (FD 44/45) TBC NTD 232 NOT PERFORMED ______ NTD STM SS1 STM JBDY 111 2. FSS 120 FT LEVEL EAST SIDE (FD EGRESS 13) JBDY GBHE NOT PERFORMED ______ SS2 3. FSS 215 FT LEVEL NORTHEAST SIDE (FD 30) NOT PERFORMED ______ SS3 283 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ NOTE -1| THE UV FIRE DETECTOR OPTICAL | AIMING DEVICE PROVIDES A | 6 DEGREE FIELD OF VIEW. THE | FIRE DETECTORS BEING AIMED | HAVE CONES LIMITING THEIR FIELD OF VIEW TO EITHER | 15 DEGREES (FD-30 AND EEFDS FD-13) OR 5 DEGREES (FD-44 AND FD-45). FOLLOWING STEPS WILL CHECK FIRE DETECTOR 44 AND 45 ALIGNMENT AND ADJUST IF REQUIRED. 03-091 DELETED -1| 284 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ NOTE FD-44 (UPPER DETECTOR) SHOULD BE AIMED TO ENABLE THE FD'S FIELD OF VIEW TO COVER THE UPPER HALF OF THE 17 INCH ET/ORB DISCONNECT. 03-092 QHGD FSS 115 FT LEVEL - FD 44 -1| 1. ATTACH SA-059-024-501 FD AIMING | DEVICE TO FD. | 2. SIGHT USING AIMING DEVICE. | 3. VERIFY EXISTING ALIGNMENT ACCEPTABLE. SFOC SE ACCEPTANCE:____________________ NOTE PERFORM NEXT STEP IF EXISTING ALIGNMENT IS UNACCEPTABLE. 03-093 QHGD FSS 115 FT LEVEL - FD 44 PETG 1. LOOSEN BRACKET HARDWARE. 2. PERFORM REALIGNMENT PER ENGINEERING DIRECTION. 3. TIGHTEN BRACKET HARDWARE WRENCH TIGHT. SFOC SE ACCEPTANCE:____________________ T:______ NOT PERFORMED ______ 285 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ NOTE FD-45 (LOWER DETECTOR) SHOULD BE AIMED TO ENABLE THE FD'S FIELD OF VIEW TO COVER THE LOWER HALF OF THE 17 INCH ET/ORB DISCONNECT. 03-094 QHGD FSS 115 FT LEVEL - FD 45 -1| 1. ATTACH SA-059-024-501 FD AIMING | DEVICE TO FD. | 2. SIGHT USING AIMING DEVICE. | 3. VERIFY EXISTING ALIGNMENT ACCEPTABLE. SFOC SE ACCEPTANCE:____________________ NOTE PERFORM NEXT STEP IF EXISTING ALIGNMENT IS UNACCEPTABLE. 03-095 QHGD FSS 115 FT LEVEL - FD 45 PETG 1. LOOSEN BRACKET HARDWARE. 2. PERFORM REALIGNMENT PER ENGINEERING DIRECTION. 3. TIGHTEN BRACKET HARDWARE WRENCH TIGHT. SFOC SE ACCEPTANCE:____________________ T:______ NOT PERFORMED ______ 286 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ NOTE -1| DELETED | 03-096 DELETED -1| NOTE -1| DELETED | 03-097 DELETED -1| 287 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ NOTE FD EGRESS 13 SHOULD BE AIMED TO ENABLE THE FD'S FIELD OF VIEW TO COVER THE AREA BELOW THE AFT OF THE VEHICLE AND BETWEEN THE BACKSIDE OF ENGINES 2 AND 3 AND THE BODY FLAP. 03-098 QHGD FSS 120 FT LEVEL - FD EGRESS 13 -1| 1. ATTACH SA-059-024-501 FD AIMING DEVICE | TO FD. | 2. SIGHT USING AIMING DEVICE. | 3. VERIFY EXISTING ALIGNMENT ACCEPTABLE. SFOC SE ACCEPTANCE:____________________ NOTE PERFORM NEXT STEP IF EXISTING ALIGNMENT IS UNACCEPTABLE. 03-099 QHGD FSS 120 FT LEVEL - FD EGRESS 13 PETG 1. LOOSEN BRACKET HARDWARE. 2. PERFORM REALIGNMENT PER ENGINEERING DIRECTION. 3. TIGHTEN BRACKET HARDWARE WRENCH TIGHT. SFOC SE ACCEPTANCE:____________________ T:______ NOT PERFORMED ______ 03-100 DELETED -1| 288 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ NOTE -1| DELETED | 03-101 DELETED -1| NOTE FD-30 SHOULD BE AIMED TO ENABLE THE FD'S FIELD OF VIEW TO COVER BOTH SIDES OF THE ET GUCP VENT LINE. 03-102 QHGD FSS 215 FT LEVEL - FD 30 -1| 1. ATTACH SA-059-024-501 FD AIMING DEVICE | TO FD. | 2. SIGHT USING AIMING DEVICE. | 3. VERIFY EXISTING ALIGNMENT ACCEPTABLE. SFOC SE ACCEPTANCE:____________________ 289 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ NOTE PERFORM NEXT STEP IF EXISTING ALIGNMENT IS UNACCEPTABLE. 03-103 QHGD FSS 215 FT LEVEL - FD 30 PETG 1. LOOSEN BRACKET HARDWARE. 2. PERFORM REALIGNMENT PER ENGINEERING DIRECTION. 3. TIGHTEN BRACKET HARDWARE WRENCH TIGHT. SFOC SE ACCEPTANCE:____________________ T:______ NOT PERFORMED ______ 03-104 DELETED -1| 290 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ 04-056 PRE-OPERATION SETUP 6 - SRB AFT SKIRT GN2 ----------------------------------------- PURGE SKID ACTIVATION --------------------- WARNING FOLLOWING STEPS HAZARDOUS DUE TO TEMPORARY ACTIVATION OF SRB AFT SKIRT GN2 PURGE. NOTE -1| THIS PRE-OPERATION SETUP IS NOT A CONSTRAINT TO S0007 VL2 CALL TO STATIONS. | DO NOT START THIS PRE-OPERATION | SETUP IF STM REQUIRES ACCESS | TO THE AREA FOR SUPPORT | PRE-OPERATION SETUPS 9, 10, | OR 11, OR PRIMARY WATER BAG | INSTALLATION. | 04-057 TBC VERIFY SRB ESP'S HAVE BEEN LOWERED. 04-057A *PAD STM VERIFY READY TO PROCEED WITH SRB AFT SKIRT -1| 111 GN2 PURGE SKID ACTIVATION. | STM JSTC | | 04-058 TBC *PAD REQUEST SHOP PERSONNEL TO REPORT ON STATION 136 CBHY ON MLP TO SUPPORT SRB AFT SKIRT GN2 PURGE *PAD BHT_ SKID ACTIVATION PRE-OPERATION SETUP. 04-059 QHT_ TBC MLP ZERO, COMPARTMENT 7A 136 CBHY SHOP PERSONNEL ON STATION READY TO SUPPORT SRB AFT SKIRT GN2 PURGE SKID ACTIVATION. 311 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ 04-060 CBHY BHT VERIFY CLEAR OF ALL PERSONNEL FROM SRB -1| LEFT AND RIGHT AFT SKIRTS AND ON MLP ZERO LEVEL TO INTERIOR PERIMETER OF SOUND SUPPRESSION SYSTEM WATER MAINS. 04-061 TBC NTD ATTENTION ON PAD _____ MLP 0 LEVEL: 232 NTD SRB LEFT AND RIGHT AFT SKIRTS GN2 PURGES WILL PA BE INITIATED AND BOTH AFT SKIRTS WILL BE FILLED WITH GASEOUS NITROGEN. LOUD VENTING WILL OCCUR AT LEFT AND RIGHT SRB AFT SKIRTS. 04-062 BHT CBHY ALL PERSONNEL CLEAR OF SRB LEFT AND RIGHT SRB CBHY TBC AFT SKIRTS AND MLP ZERO LEVEL CONTROL AREAS. 136 REQUEST SAFETY CONCURRENCE TO FLOW GN2 INTO TBC NTD SRB AFT SKIRTS. 232 NTD *SCC 311.1 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ THIS PAGE INTENTIONALLY BLANK 311.2 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ 04-063 NTD TBC YOU HAVE SAFETY CONCURRENCE TO PROCEED WITH 232 SRB AFT SKIRT GN2 PURGE SKID AND SYSTEM TBC CBHY ACTIVATION. 136 SRB AFT SKIRT GN2 PURGE ACTIVATION ---------------------------------- PART 1 - MLP ELECTRICAL AND VALVING SETUPS ------------------------------------------ 04-064 CBHY QHT_ MLP COMPARTMENT 7A 187 GSE SYSTEM CONFIGURATION SETUP POWER DISTRIBUTION RACK 6673 POSITION ALL CIRCUIT BREAKER TOGGLE SWITCHES - UP (ON) T:______ 04-065 CBHY QHT_ MLP COMPARTMENT 7A 187 RECORD 28 VOLT DC POWER STATUS RACK 6820 22D200 POWER SUPPLY RECORD__________ (ON OR OFF) RACK 6822 (GN2 PURGE) 22D380 CIRCUIT BREAKER RECORD__________ (ON OR OFF) RACK 6822 (GN2 PURGE) 22D380X CIRCUIT BREAKER RECORD__________ (ON OR OFF) T:______ 312 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ 05-000 PRE-OPERATION SETUPS - INTEGRATED --------------------------------- 05-001 PRE-OPERATION SETUP 1 - SAFETY/FACILITY/ --------------------------------------- FIRE WALKDOWN ------------- 05-002 NTD OTC PERFORM INTEGRATED PRE-OPERATION SETUP 1 - 232 SAFETY/FACILITY/FIRE WALKDOWN. OTC *PAD NET 110 05-003 *PAD REVIEW PRTL (POTENTIAL RE-OCCURENCE TRACKING LOG) FROM BOTH PADS A AND B FOR APPLICABLE RE-OCCURENCE ITEMS. ITEMS THAT ARE DETERMINED APPLICABLE WILL BE ENTERED ON APPENDIX K. 05-004 *PAD DEVELOP DISCREPANCY LIST IN APPENDIX K (S0007VL4). 05-005 NTD OTC HAVE WALKDOWN PARTICIPANTS MEET WITH *PAD FIRE 232 STM AT FSS ELEVATORS ON PAD SURFACE IN 30 MINUTES. *SCC GSE OPS *SCC *PSE FACILITY OPS NET SFOC SAFETY 105 QUALITY CONTROL OTC *PAD FIRE INSPECTOR 132 SITE TEST CONDUCTOR (TTL) STM JSTC NASA OPS (NPM) 111 TECHS (2 EA WITH CSR 590 CERTIFICATION) NET PSTM 104 JSTC JFIR 114 05-006 NTD ATTENTION ON PAD___: PA ALL PERSONNEL SUPPORTING SAFETY/FACILITY/FIRE WALKDOWN MEET WITH *PAD AT FSS ELEVATORS ON PAD SURFACE IN 30 MINUTES. 05-007 *PAD VERIFY LISTED PARTICIPANTS PRESENT FOR START OF WALKDOWN AND PERFORM PRE-TASK BRIEFING. TTL ______ 319 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 PRE-OPERATION SETUP INSTRUCTIONS SEQ CMD RESP DESCRIPTION VERIF. -------- ---- ---- ------------------------------------------- ------ NOTE -1| BUY-OFF (CLOSURE) OF APPENDIX K DISCREPANCY LIST ITEMS IS NOT REQUIRED FOR COMPLETION OF PRE-OPERATION SETUP. THESE ITEMS WILL BE WORKED UP TO INTEGRATED OPERATIONS SUPPORT SETUP 5 AND CLOSURES OF APPENDIX K WILL CONSTRAIN CLOSURE OF OPERATION SUPPORT SETUP 5. | ANY DISCREPANCY NOTED BY ANY | OF THE WALKDOWN PARTICIPANTS | WILL BE RECORDED IN APPENDIX K, | UNLESS DISCREPANCY IS IDENTIFIED | AS BEING RESOLVED BY SCHEDULED | WORK SUPPORTING S0007 PREPARATIONS | FOR LAUNCH. | 05-008 *PAD ALL ALL DISCREPANCIES WILL BE RECORDED IN BUY COPY OF APPENDIX K. (S0007VL4). 05-009 *PAD ALL INSPECT AND VERIFY FOR EACH AREA OF WALKDOWN THAT: 1. COMBUSTIBLE MATERIALS HAVE BEEN REMOVED FROM AREA. 2. NO SPARK/FLAME PRODUCING EQUIPMENT IN AREA. 3. FLEXHOSES, CABLES, LINES, ETC PROPERLY SECURED. 4. SAFETY SHOWERS AND EYE WASH FOUNTAINS OPERATIONAL. 5. WORK AREAS AND TRAFFIC ROUTES FREE OF HAZARDS/CLUTTER. 6. ALL LOOSE ITEMS AND DEBRIS (FOD) SECURED OR REMOVED. 7. CONSTRUCTION CONTRACTOR EQUIPMENT SECURED OR REMOVED. 320 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 OPERATION SUPPORT SETUP INSTRUCTIONS SEQ TIME CMD RESP DESCRIPTION VERIF. -------- ---------- ---- ---- --------------------------------- ------ 08-005 PQCG MLP COMPARTMENT 44B PERFORM INTEGRITY VERIFICATION INSPECTION OF FOLLOWING ELECTRICAL PANEL: 6771 (A.C. POWER PANEL) QW:_____ 08-006 DELETED -1| 08-007 PQCG *PAD ORBITER OPERATION SUPPORT SETUP 1 - *PAD OTC MPS/SSME MLP PATCH RACK - DISTRIBUTER 132 CMQC PANEL INTEGRITY VERIFICATIONS COMPLETE. QV:_____ 351 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 OPERATION SUPPORT SETUP INSTRUCTIONS SEQ TIME CMD RESP DESCRIPTION VERIF. -------- ---------- ---- ---- --------------------------------- ------ THIS PAGE INTENTIONALLY BLANK 352 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 OPERATION SUPPORT SETUP INSTRUCTIONS SEQ TIME CMD RESP DESCRIPTION VERIF. -------- ---------- ---- ---- --------------------------------- ------ NOTE PERFORM NEXT STEP IF EDO WCS IS INSTALLED. 08-122 OTC MS3 PANEL WCS (COMMODE AREA) 132 WCS AIR DIVERTER VALVE - CAN RETEST/TEST SW - CENTER URINE DIVERTER VALVE - FAN SEP 1 VACUUM VENT VALVE - CLOSED USER PANEL URINAL SEL SW - OFF WCS PWR SEL (2 SWITCHES) - OFF COMPACT PB - AS IS FAN POWER - AUTO (CENTER) VERIFY ALL LIGHTS OFF NOT PERFORMED ______ NOTE -1| DELETED | 08-123 DELETED -1| WASTE MANAGEMENT STATION SWITCHLIST ----------------------------------- COMPLETE -------- 421 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 OPERATION SUPPORT SETUP INSTRUCTIONS SEQ TIME CMD RESP DESCRIPTION VERIF. -------- ---------- ---- ---- --------------------------------- ------ 08-124 *PAD OQCV PERFORM FLIGHT CLOSEOUT INSPECTION OF WMS PER FOLLOWING: 1. VERIFY NON-FLIGHT ITEMS EITHER REMOVED OR RECORDED IN TIR SYSTEM. INSPECT WHERE ACCESSIBLE WITHOUT DISCONNECTING OR NULLIFYING PRIOR INSPECTION ACCEPTANCE, EXCLUDES PRIOR CLOSEOUT AND VERIFY: 2. ELECTRICAL AND MECHANICAL CONNECTORS PROTECTED WITH CAPS OR COVERS NOT CONNECTED. 3. SERVICING TEST PORTS CAPPED WHEN NOT REQUIRED TO FUNCTION FOR SCHEDULED TEST. 4. HATCHES AND ACCESS PANELS IN PLACE AND SECURED WHEN NOT REQUIRED FOR SCHEDULE TEST. 5. ELECTRICAL WIRES, CABLES AND HARNESSE FREE OF NICKS, CUTS, SCUFFS, COATING DENTS, BLISTERS, GROSS DISCOLORATION, SHARP BENDS, SECURE SPOT TIES AND CABLE CLAMPS, AND ENSURE ADEQUATE CLEARANCE FROM BRACKETS, FAIRINGS, AND LIGHTENING HOLES. 6. ELECTRICAL COMPONENTS INSULATION FREE OF CUTS, RIPS OR TEARS. 7. ELECTRICAL GROUNDING STRAPS/BRAIDS NOT FRAYED OR DAMAGED. 8. FLEXHOSES SECURE AND NO BROKEN OR FRAYED STRANDS, FLAT SPOTS OR KINKS. 9. STRUTS/SUPPORTS FREE OF DINGS, DENTS, GOUGES OR SCRATCHES. 10. SWITCHES, ROTATING KNOBS AND CIRCUIT BREAKERS FREE OF DAMAGE AND ATTACHING HARDWARE NOT LOOSE OR MISSING. 422 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 OPERATION SUPPORT SETUP INSTRUCTIONS SEQ TIME CMD RESP DESCRIPTION VERIF. -------- ---------- ---- ---- --------------------------------- ------ 08-175 OPERATION SUPPORT SETUP 15 - PAYLOAD | ------------------------------------ | BAY PURGE VERIFICATION (IUS) | ---------------------------- | | NOTE | | PERFORM NEXT FOUR STEPS FOR | IUS/AXAF (STS-93). | | THE NEXT STEP WILL BE | PERFORMED WHEN VEHICLE IS | BEING PURGED WITH AIR. STEP | MAY BE PERFORMED BY EITHER | CPVD OR PPVM. IF CPVD NOT | ON STATION, CALL PPVM. | | 08-175A PTC OTC VERIFY ORBITER PAYLOAD BAY PURGE -1| 132 IS ON AND WITHIN FOLLOWING SPECS: | OTC CPVD | PPVM 1. FLOW RATE: 218.5-241.5 LBS/MIN | INTERFACE TEMP: 65.5 - 70.5 DEG F | HUMIDITY: AIR - EQUAL TO OR | LESS THAN 29 GRAINS | H2O/LB | | OMRSD P018DB.010 | OMRSD P330DB.100 (AXAF) | | 2. IF READINGS PROVIDED BY PPVM | TQW:____| | NOT PERFORMED ______| SS2 | | NOT PERFORMED ______| | 447 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 OPERATION SUPPORT SETUP INSTRUCTIONS SEQ TIME CMD RESP DESCRIPTION VERIF. -------- ---------- ---- ---- --------------------------------- ------ NOTE -1| | THE NEXT THREE STEPS WILL | BE PERFORMED WHEN VEHICLE | IS BEING PURGED WITH GN2. | | NOTED REQUIREMENT SATISFIED | BY COMPLETION OF NEXT STEPS. | | OMRS P018DB.010 | OMRS P330DB.100 (AXAF) | | 08-175B PTC OTC VERIFY ORBITER PAYLOAD BAY PURGE -1| 132 IS ON AND WITHIN FOLLOWING SPECS: | OTC CPVD | FLOW RATE: 218.5-241.5 LBS/MIN | INTERFACE TEMP: 65.5-70.5 DEG F | | NOT PERFORMED ______| | 08-175C OTC NTD VERIFY HUMIDITY EQUAL TO OR PNU -1| 232 LESS THAN 1 GRAIN H2O/LB. | NTD STM | STM JSTC | 111 | JSTC GSPN | 114 | NOT PERFORMED ______| | 08-175D NOTED REQUIREMENTS COMPLETE. -1| | OMRSD P018DB.010 | OMRSD P330DB.100 (AXAF) | | NOT PERFORMED ______| | 08-175E CPVD OTC ORBITER OPERATION SUPPORT SETUP 15 - -1| 132 PAYLOAD BAY PURGE VERIFICATION | OTC PTC COMPLETE. | CMQC | CPVD ______| 448 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 OPERATION SUPPORT SETUP INSTRUCTIONS SEQ TIME CMD RESP DESCRIPTION VERIF. -------- ---------- ---- ---- --------------------------------- ------ 10-071 OPERATION SUPPORT SETUP 5 - SRB AFT ----------------------------------- SKIRT GN2 PURGE ACTIVATION -------------------------- NOTE RECORD VERIFICATIONS IN TABLE 1 | OF THIS OPERATION SUPPORT SETUP. | DO NOT PERFORM THIS OPERATION SUPPORT SETUP IF FLEX BEARING PURGE NOT REQUIRED. OPERATION SUPPORT SETUP 5 NOT PERFORMED ______ 10-072 CBHY TBC READY TO PROCEED WITH SRB AFT SKIRT 136 GN2 PURGE ACTIVATION. REQUEST TBC NTD CONCURRENCE TO CLEAR. 232 NTD *SCC 10-073 CBHY BHT_ CLEAR ALL PERSONNEL FROM SRB AFT SKIRT AREA TO INTERIOR OF SOUND SUPPRESSION PIPES, INSTALL ROPES AND HAZARDOUS WARNING SIGNS FOR SRB AFT SKIRT GN2 PURGE ACTIVATION. 10-074 NTD ATTENTION ON MLP ZERO LEVEL: PA ALL PERSONNEL CLEAR SRB AFT SKIRTS FOR GN2 PURGE ACTIVATION. 10-075 TASK TEAM LEADER/DESIGNATED FLOOR | LEADER (DFL) PERFORM SAFETY INSPECTION OF THE LOCAL CONTROL AREA AND EGRESS ROUTE(S) FROM CONTROL AREA. VERIFY NO DISCREPANCIES WHICH AFFECT THE OPERATION AND/OR SAFE EGRESS FROM CONTROL AREA. 10-076 BHT_ CBHY CONTROLS ESTABLISHED ON SRB AFT -1| CBHY TBC SKIRTS AND ALL PERSONNEL CLEAR, 136 ROPES AND HAZARDOUS WARNING SIGNS TBC NTD POSTED. REQUEST SAFETY CONCURRENCE 232 TO ACTIVATE SRB AFT SKIRT GN2 NTD *SCC PURGE. T:______| 617 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 OPERATION SUPPORT SETUP INSTRUCTIONS SEQ TIME CMD RESP DESCRIPTION VERIF. -------- ---------- ---- ---- --------------------------------- ------ 10-077 *SCC NTD YOU HAVE SAFETY CONCURRENCE TO PROCEED 232 WITH SRB AFT SKIRT GN2 PURGE. NTD TBC TBC CBHY 136 CBHY BHT_ WARNING GN2 FLOW TO SRB AFT SKIRTS WILL BE ACTIVATED. ALL PERSONNEL MUST REMAIN CLEAR OF AFT SKIRTS DURING FLOW. 10-078 TBC CBHY ACTIVATE SRB AFT SKIRT GN2 PURGE. 136 10-079 GBHY GSPN SRB AFT SKIRT GN2 FLOW WILL COMMENCE 114 MOMENTARILY. 10-080 CBHY CONSOLE KYBD HOME CMD KEY - PRESS BAT04 PERF PGM KEY 10-081 CBHY CURSOR CNTL (BAT04) SRB AFT SKIRT GN2 PURGE DC PWR PRI - ON SEC - ON 10-082 CBHY CURSOR CNTL (BAT04) SRB AFT SKIRT GN2 PURGE (VALVING) (MAIN) PRI - OP SEC - OP HEATER (ARROWS) ADJUST SET POINT TO 70 +/-5 HEATER CMD - ON 618 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 OPERATION SUPPORT SETUP INSTRUCTIONS SEQ TIME CMD RESP DESCRIPTION VERIF. -------- ---------- ---- ---- --------------------------------- ------ 11-028 OPERATION SUPPORT SETUP 3 - FINAL --------------------------------- TPS ENGINEERING DEBRIS WALKDOWN ------------------------------- NOTE PERFORM FINAL WALKDOWN AFTER RSS ROTATION, 'O' LEVEL HAND RAILS REMOVED, TSM CLEANING COMPLETE AND ESP'S REMOVED. 11-029 NTD OTC PERFORM TPS ENGINEERING 232 STM DEBRIS WALKDOWN PER INTEGRATED *SCC OPERATION SUPPORT SETUP 3 UNDER OTC *PAD DIRECTION OF NASA TPS ENGINEER. 132 STM PSTM NET 104 *SCC *PSE NET 105 11-030 TTL PERFORM FOLLOWING: -1| 1. VERIFY FOLLOWING PERSONNEL PRESENT FOR WALKDOWN: | SFOC TPS ENGR NASA TPS ENGR SFOC TECH OPS SFOC QUALITY SFOC SAFETY PSTM NASA FINAL INSP TEAM REP (OPT) | TTL ______ SS1 2. OBTAIN A COPY OF CURRENT APPENDIX K (S0007VL4) WALKDOWN DISCREPANCY LIST FROM PAD LEADER. 633 VOLUME 1 OF 5 OMI NO. - S0007VL1 DATE: 07-01-99 REV. - AT-1 OPERATION SUPPORT SETUP INSTRUCTIONS SEQ TIME CMD RESP DESCRIPTION VERIF. -------- ---------- ---- ---- --------------------------------- ------ 11-030 3. INSPECT FOLLOWING AREAS CON'T FOR DEBRIS. A. MLP ZERO LEVEL 1. PERIMETER DECKING/GUTTERS 2. LH2/LOX TSM EXTERIOR 3. LEFT/RIGHT SRB FLAME HOLES, SS PIPING, AND UNDER BLAST SHIELDS 4. SSME FLAME HOLE AND UNDER BLAST SHIELDS B. PAD SURFACE C. NORTH AND SOUTH FLAME TRENCH TTL ______ 11-031 ANY NOTED DEBRIS WILL BE PICKED UP BY TECH OPS OR ADDED TO APPENDIX K AND REPORTED TO *PAD TTL ______ 11-032 FINAL TPS ENGINEERING DEBRIS WALKDOWN COMPLETE. ALL DISCREPANCIES HAVE BEEN DOCUMENTED IN S0007VL4 APPENDIX K. SFOC TPS ENGR__________________ SFOC TECH OPS__________________ NASA SYS ENGR_________________ SFOC SAFETY___________________ SFOC QUALITY___________________ PSTM__________________________ TTL ______ 634 DATE: 1999-07-02 15.24.14 S0007VL1 SHUTTLE COUNTDOWN (LPS) DISTRIBUTION F - FINAL TAB CHOATE K. GRANT SA21 USH-440X BOEING - ROCKETDYNE DIVI UNITED SPACE ALLIANCE MARSHALL SPACE FLIGHT CE 600 GEMINI BLDG 4202, RM 405 HOUSTON, TX 77058 HUNTSVILLE, AL 35812 JERRY L. GREENWOOD TONY IPPOLITO 3731 MILA MICHOUD ASSY FACILITY NEAL E. VANSCYOC LOCKHEED MARTIN F224 P.O. BOX 29304 JAMES B. PARKS NEW ORLEANS, LA 70189 PK-J-B ALEX RODRIGUEZ.......3 PHIL LINTEREUR........................2 ZK-86 F264 DEBBIE HAHN PETE WILSON NN-M2 ZK-07 MEGAN MISCHKOT JAMES REED N/A EY-C MICHOUD ASSEMBLY FACILIT ROBERT L. WRIGHT P.O. BOX 29300 CSR-4222B NEW ORLEANS, LA 70189 WHIT BARTLETT DEPT 4250 PK-D2 JILL JAHNKOW..........2 FERDINAND JONES FA-99 AC-58 BOEING NORTH AMERICAN BOEING NORTH AMERICAN MISSION SUPPORT ROOM 6633 CANOGA AVE 12214 LAKEWOOD BLVD CANOGA PARK, CA 91304 DOWNEY, CA 90241 SUSAN FRAHM JOANNE CREECH BOC-005 BOC-022 CALVIN J. CULBERTSON..................2 CHRIS WEAVER.........6 FC-51 PZ-L CCAS, FL 32899 LISA A. MALONE PA-MSB BRUCE D. BOUTON 8A-44 BOEING DEFENSE & SPACE G P.O. BOX 3999 SEATTLE, WA 98124-2499 TOTAL QTY: 271 FOR CHANGES TO THIS DISTRIBUTION LIST, CONTACT: MARY M. HESTER , USK-187, (407) 861-3301 EXT ELIZABETH C. KLOS , USK-187, (407) 861-3430 EXT 1 DATE: 1999-07-02 15.24.14 S0007VL1 SHUTTLE COUNTDOWN (LPS) DISTRIBUTION F - FINAL AFQA/LGQAB/P. MCDANIEL NN-M1 BA/FC-50/W. BRAGG.....................2 NN-M2 BA/FC-51/ELS DATA FILES NN-M3 BA/FC-51/J. HAGOOD....................2 THIO-LSS/BRIAN ST. AUBIN BA/FC-51/J. LEWIS.....................2 USBI-LSS/LIBRARY BA/FC-51/N. BIHR......................3 USK-078/CCC, C-1 PNEU BNA SPACEHAB/NANCY CRABTREE...........2 USK-078/CCC, C-1 WATER SPACEHAB, INC USK-078/CCC, C-2 HVAC 620 MAGELLAN RD USK-078/CCC, C-3 POWER CAPE CANAVERAL, FL 32920 USK-078/CCC, INTEGRATION C07A/J. LECHER USK-225/JODI SILLS JSC, TX 77058 USK-391/SAFETY OPS (PAD B) EI-C-C/NSF CONSOLE USK-550/VITT OFFICE......2 EI-C-D/NASA VAB SAFETY ZA03/DAVID BARNES EI-C-F/NASA OPF SAFETY BOEING NORTH AMERICAN ESMC-SEO/CAMPBELL 555 DISCOVERY DRIVE LLOYD MUSTIN SSM HUNTSVILLE, AL 35806 MAIL STOP AE26 3 SLS/DOOT/CAPT. G. FENTRESS BOEING NORTH AMERICAN 3 SLS/MA/B. STRACENER....2 SPACE SYSTEMS DIV. AIR-FORCE CCAFS P.O. BOX 7009 N/A DOWNEY, CA 90241-7009 45 RANS/DOOB MS-E68/R. BAKES (CCAFS) THIOKOL CORP. PHILLIPS PARKWAY/10400 P.O. BOX 707 PATRICK AFB, FL 32925 BRIGHAM CITY, UT 84302-0707 AUTO-SUPPORT REQUIREMENTS-SYS MS3/LIBRARY USK-068 JSC, TX 77058 CCC LIBRARY..............3 MV2/D. STAMPER USK-093 JSC, TX 77058 MISSION SUPPORT MV3/KENNETH BROWN SGS-347 JSC, TX 77058 EG&G PROTECTIVESYSTEMS NASA/JSC..............................2 BOC-326 C/O TRANSPORTATION OFFICE PAD ELECTRICAL-SHOP BUILDING 420 USK-175 HOUSTON, TX 77058 SECTION NASACOMM/RFSYSTEMS ATTN: DA82/MARY C. THOMAS PK-F3 BLDG 30M, ROOM 235 NASA-FLT ELECTR-SYS-SECT NN-L/PAYLOAD ENGINEERING PK-F 1 DATE: 1999-07-02 15.24.14 S0007VL1 SHUTTLE COUNTDOWN (LPS) DISTRIBUTION F - FINAL FLT-CREW EQUIP PAD-B SWING-ARMS-SHOP USK-264 USK-425 FLOW DIRECTOR-OFFICE TECHNICAL DOC-CTR.......50 PH-B2 USK-038 SECTION NASAECLSSSYSTEM TSMO SITE-MGRS PK-G5 USK-299 BOEING P/L-TEST-CONDUCTOR.............3 TSMO OMD F214 USK-075 GUIDANCE-AND NAVIGATION USA INSTRUMENTATION......2 USK-195 USK-194 GEL LCC-RM-3R18 VITT OFFICE USK-542 F204 LCC HAZ-GAS O&C BLDG USK-542 SWING ARMS-ENG'G ORB MECHANISM USK-290 PK-H5 ET MECHANICAL-ENG NASA QA-FR1 USK-251 USK-268 ET LH2PAD-A OTC ORBTESTCONDUCTOR..................4 USK-174 USK-023 ET LH2PAD-B SPC PAD-SAFETY USK-390 USK-257 ET-LOX PAD-A TEST-OPS PAD-A USK-173 USK-307 MEQ ORB-MECHANISMS-ENG TEST-OPS PAD-B USK-408 USK-389 OMS/RCS ENG-PADA BRANCH INSTRUM.&P/LSYS................2 USK-484 PK-F3 OMS/RCS ENG-PADB PNEUMATICS ENGINEERING USK-347 USK-043 CENTRL WRK-PKG-BLD OFFICE NASAFIRE/RESCUE USK-409 IM-SPS-A COMM CONTROL.............2 PAD SWING-ARMS-SHOP USK-145 USK-398 TSMO PAD-A SFOC SAFETY-CONSOLE USK-076 USK-399 TSMO PAD-B SUPV-SAFETY RELIABILITY-ENGR USK-404 USK-291 TSMO SUPV-STM......3 USK-299 1 DATE: 1999-07-02 15.24.14 S0007VL1 SHUTTLE COUNTDOWN (LPS) DISTRIBUTION F - FINAL FRANK A. DEBERNARDO TODD M. GRACOM USK-116 USK-195 NEAL R. GRIFFITH PAUL R. GRATSCH....2 USK-112 USK-195 DON GARCEAU SECUR/041399 VEVERA USK-109 USK-229 THOMAS E. JACOBS......................2 CHARLES J. HANNAS USK-107 USK-192 JIM TOWNSEND EARL D. COOLEY USK-108 USK-269 SHOE SHOEMAKER BOB DOUGERT.......2 USK-144 USK-356 PAT CHAPPELL DEAN T. TYRE USK-074 USK-421 DENNIS E. LOHAUS STEVE VELLIGAN USK-069 USK-213 HAL L. SNOW RANDY DUNCAN USK-171 USK-196 RICHARD H. MURRAY.....................2 DON GREEN.........2 USK-414 USK-043 ROBERT RODRIGUEZ PEGGY S. HATTAWAY USK-198 USK-246 TOM WELLS.............................2 GARY A. WOODS USK-420 USK-281 MARTIN L. CARLSON ANN M. MICKLOS USK-420 USK-443 JUDY HOOPER...........................3 TERM/SECUR POSTON USK-247 USK-598 STEVE GODFREY PAUL E. BRANDT USK-241 USK-111 BILL NUTTER...........................5 OZZIE FISH........2 USK-214 USK-314 JANIENE L. PAPE DONALD L. CROUSE II USK-284 USK-254 PAUL L. QUANDT ANDY BUNDY USK-356 PK-E3 CHARLES E. SWEENEY DAVID R. SCHECHTER USK-424 PZ-C 1 DATE: 1999-07-02 15.24.14 S0007VL1 SHUTTLE COUNTDOWN (LPS) DISTRIBUTION F - FINAL JIMBO BOLTON OLAN J. BERTRAND USBI-LSS CA4 BILL CLEVER II HOUSTON, TX 77058 SK KEN FORD...........2 KATHLEEN A. CONWAY USK-637 USK-669 RICHARD MIZELL TERRI L. HERST PK-F6 PK-D LARRY E. WILSON ED MANGO USK-412 PK-D2 ERVIN G. WALKER SCOTT CHANDLER JCI-VITC-2 PK-E4 ANGELO PACE MICHAEL GARSKE USK-682 DF24 RANDY DAVIES JSC, TX 77058 CSR-3200 AL DIAZ CAPE CANAVERAL AFS, FL 32899 PK-F RONALD W. WETMORE BOB BEIL MMC-15 PK-G3 HAROLD E. REED ANDY DIBBERN JJ-3-B PK-G6 CHUCK GIVENS PETE CHITKO BOC-342 PK-H6 RAYMOND G. PREECE GREG KATNIK ZK-07 PK-H7 RAY W. NUSS JORGE E. RIVERA EV4 PK-H7 JOHNSON SPACE CENTER PHIL WEBER HOUSTON, TX 77058 PK-H6 ROBERT B. LUECKING PAT MARKEY ZK-86 PK-J MATTHEW J. HOFMANN JOHN W. DOYLE ROC-LSS USK-714 JIM ALLAMON RENEE HART ZK-21 USK-669 CANDICE F. NORMAN....2 BOBBY E. ORR BOC-349 USK-607 TOM HILL ASC/ERD-FL